More than 拢15bn worth of work has been dished out
At least 拢15bn of work across and more than 35 contracts have already been handed to construction firms by HS2
Among the firms to already have been handed work on the project are contractors including Balfour Beatty, Mace, Vinci and Skanska, as well as consultants Lendlease, Mott MacDonald and CH2M.
Here is HS2鈥檚 list of who鈥檚 got what so far.
>> Analysis: North and Midlands pledge to build on broken rail promises
>> Also read: On site: HS2鈥檚 groundbreaking project under way beneath the Chilterns
Already awarded construction and systems contracts:
Description | Award Date | Tenderers / Awarded Suppliers | Indicative Budget |
---|---|---|---|
Utility works - Euston Station | Q1 2022 | Barhale | TBC |
Station lifts and escalators framework | Q1 2022 | TK Elevator | 拢316尘 |
EKFB precast tunnel sections | Q4 2021 | Stanton Precast | TBC |
Production of precast concrete segments (south) | Q3 2021 | Pacadar UK | TBC |
Chiltern Tunnels - headhouse and ventilation shaft construction | Q3 2021 | Keltbray | TBC |
Enabling civils works 鈥 Package 2 | Q3 2021 | Kier | 拢50尘 |
HS2 Phase One Stations: Construction Partner (Curzon Street) | Q2 2021 | Mace and Dragados | 拢570尘 |
Early environmental works contract | Q2 2021 | Balfour Beatty | 拢52尘 |
Geotechnical work on the C1 package of HS2 | Q1 2021 | Keller Group and VSL International | 拢167尘 |
Detailed design of civil engineering work C2/C3 | Q4 2020 | ASC (Arcadis, Setec and Cowi) (Awarded by EKFB) | TBC |
HS2 modular track contract | Q4 2020 | Porr UK and Aggregate Industries | 拢260尘 |
Commercial management | Q3 2020 | Gleeds | 拢105尘 |
Programme controls | Q3 2020 | Atkins | 拢126尘 |
Civil Design & Environmental Services | Q4 2015 | Arup | TBC |
Civil Engineering: Brackley to South Portal of Long Itchington Wood Tunnel (C3) | Q3 2017 | EKFB JV (Eiffage, Kier, Bam Nuttall and Ferrovial) | 拢600m - 拢900m |
Civil Engineering: Chiltern Tunnels and Colne Valley Viaduct (C1) | Q3 2017 | Align JV (Bouygues, VolkerFitzpatrick and Sir Robert McAlpine) | 拢800m - 拢1.3bn |
Civil Engineering: Delta Junction to West Coast Main Line Tie -In (N2) | Q3 2017 | BBV JV (Balfour Beatty and Vinci) | 拢900m - 拢1.5产苍 |
Civil Engineering: Euston Tunnels & Approaches (S1) | Q3 2017 | SCS JV (Skanska Construction, Costain and Strabag) | 拢600m - 拢900m |
Civil Engineering: Long Itchington Wood Tunnel South Portal to Delta Junction and Birmingham Spur (N1) | Q3 2017 | BBV JV (Balfour Beatty and Vinci) | 拢900m - 拢1.5产苍 |
Civil Engineering: North Portal of Chiltern Tunnels To Brackley (C2) | Q3 2017 | EKFB JV (Eiffage, Kier, Bam Nuttall and Ferrovial) | 拢800m - 拢1.3bn |
Civil Engineering: Northolt Tunnels (S2) | Q3 2017 | SCS JV (Skanska Construction, Costain and Strabag) | 拢850m - 拢1.4bn |
Enabling Works Central | Q4 2016 | Fusion JV (Morgan Sindall, Bam Nuttall and Ferrovial) | 拢300尘 |
Enabling Works North | Q4 2016 | LM JV (Laing O鈥橰ourke and J. Murphy & Sons) | 拢300尘 |
Enabling Works South | Q4 2016 | CS JV (Costain and Skanska) | 拢300尘 |
Engineering Delivery Partner (EDP) | Q1 2016 | CH2M Hill, Atkins and Sener Engineering and System | 拢250m - 拢350m |
Euston Over Site Development Master Development Partner | Q1 2018 | Lendlease | &驳迟;拢1产苍 |
Ground Investigation Core & Sample Storage Facility | Q1 2016 | ALS Petrophysics | &濒迟;拢5尘 |
Ground Investigation Works Framework Agreement | Q1 2015 | 鈥 Bam Ritchies 鈥 Environmental Scientifics Group 鈥 Fugro Seacore 鈥 Soil Engineering Geoservices 鈥 Structural Soils 鈥 Allied Exploration & Geotechnics 鈥 Farmer Associates 鈥 RPS Planning and Development 鈥 WYG |
拢50尘 - 拢100m |
HS2 Phase One Stations: Construction Partner (Euston) | Q1 2019 | Mace and Dragados | 拢1.5产苍 |
HS2 Phase One Stations: Construction Partner Contracts (Old Oak Common) | Q3 2019 | Balfour Beatty, Vinci and Systra | 拢1.1产苍 |
Party Wall Award Services for the Vezey Wing of the National Temperance Hospital | Q2 2016 | Lambert Smith Hampton | &濒迟;拢2尘 |
Phase One Stations Professional Services Design Contracts (Birmingham Curzon Street Station) | Q1 2018 | WSP | 拢18m - 拢30m |
Phase One Stations Professional Services Design Contracts (Birmingham Interchange Station) | Q1 2018 | Arup | 拢13- 拢23m |
Phase One Stations Professional Services Design Contracts (London Euston Station) | Q1 2018 | Arup | 拢87- 拢98m |
Phase One Stations Professional Services Design Contracts (London Old Oak Common Station) | Q1 2018 | WSP | 拢47m - 拢70m |
Phase One: Plant Material | Q4 2016 | W Crowder & Sons | 拢5m - 拢9m |
Phase Two Development Partner | Q4 2016 | Bechtel | 拢130m - 拢170m |
Phase Two Professional Services Consultants - Civils design and environmental services | Q1 2017 | Lot 1 鈥 Mott MacDonald with WSP Lot 2 鈥 Aecom with Capita & Ingenieria y Economia Lot 3 鈥 Arup |
拢280尘-拢350尘 |
Procurement of routewide provision of Specialist Security Services | Q4 2017 | Control Risks | 拢32尘-42尘 |
Railway Systems Design Services Framework | Q4 2015 | WSP | TBC |
Site Access, Land Referencing and Landowner Engagement Framework: Work Package (Phase 2a - West Midlands to Crewe) |
Q4 2015 | Mouchel, Arup, Aecom, WSP | TBC |