More than £15bn worth of work has been dished out
At least £15bn of work across and more than 35 contracts have already been handed to construction firms by HS2
Among the firms to already have been handed work on the project are contractors including Balfour Beatty, Mace, Vinci and Skanska, as well as consultants Lendlease, Mott MacDonald and CH2M.
Here is HS2’s list of who’s got what so far.
>> Analysis: North and Midlands pledge to build on broken rail promises
>> Also read: On site: HS2’s groundbreaking project under way beneath the Chilterns
Already awarded construction and systems contracts:
Description | Award Date | Tenderers / Awarded Suppliers | Indicative Budget |
---|---|---|---|
Utility works - Euston Station | Q1 2022 | Barhale | TBC |
Station lifts and escalators framework | Q1 2022 | TK Elevator | £316³¾ |
EKFB precast tunnel sections | Q4 2021 | Stanton Precast | TBC |
Production of precast concrete segments (south) | Q3 2021 | Pacadar UK | TBC |
Chiltern Tunnels - headhouse and ventilation shaft construction | Q3 2021 | Keltbray | TBC |
Enabling civils works – Package 2 | Q3 2021 | Kier | £50³¾ |
HS2 Phase One Stations: Construction Partner (Curzon Street) | Q2 2021 | Mace and Dragados | £570³¾ |
Early environmental works contract | Q2 2021 | Balfour Beatty | £52³¾ |
Geotechnical work on the C1 package of HS2 | Q1 2021 | Keller Group and VSL International | £167³¾ |
Detailed design of civil engineering work C2/C3 | Q4 2020 | ASC (Arcadis, Setec and Cowi) (Awarded by EKFB) | TBC |
HS2 modular track contract | Q4 2020 | Porr UK and Aggregate Industries | £260³¾ |
Commercial management | Q3 2020 | Gleeds | £105³¾ |
Programme controls | Q3 2020 | Atkins | £126³¾ |
Civil Design & Environmental Services | Q4 2015 | Arup | TBC |
Civil Engineering: Brackley to South Portal of Long Itchington Wood Tunnel (C3) | Q3 2017 | EKFB JV (Eiffage, Kier, Bam Nuttall and Ferrovial) | £600m - £900m |
Civil Engineering: Chiltern Tunnels and Colne Valley Viaduct (C1) | Q3 2017 | Align JV (Bouygues, VolkerFitzpatrick and Sir Robert McAlpine) | £800m - £1.3bn |
Civil Engineering: Delta Junction to West Coast Main Line Tie -In (N2) | Q3 2017 | BBV JV (Balfour Beatty and Vinci) | £900m - £1.5²ú²Ô |
Civil Engineering: Euston Tunnels & Approaches (S1) | Q3 2017 | SCS JV (Skanska Construction, Costain and Strabag) | £600m - £900m |
Civil Engineering: Long Itchington Wood Tunnel South Portal to Delta Junction and Birmingham Spur (N1) | Q3 2017 | BBV JV (Balfour Beatty and Vinci) | £900m - £1.5²ú²Ô |
Civil Engineering: North Portal of Chiltern Tunnels To Brackley (C2) | Q3 2017 | EKFB JV (Eiffage, Kier, Bam Nuttall and Ferrovial) | £800m - £1.3bn |
Civil Engineering: Northolt Tunnels (S2) | Q3 2017 | SCS JV (Skanska Construction, Costain and Strabag) | £850m - £1.4bn |
Enabling Works Central | Q4 2016 | Fusion JV (Morgan Sindall, Bam Nuttall and Ferrovial) | £300³¾ |
Enabling Works North | Q4 2016 | LM JV (Laing O’Rourke and J. Murphy & Sons) | £300³¾ |
Enabling Works South | Q4 2016 | CS JV (Costain and Skanska) | £300³¾ |
Engineering Delivery Partner (EDP) | Q1 2016 | CH2M Hill, Atkins and Sener Engineering and System | £250m - £350m |
Euston Over Site Development Master Development Partner | Q1 2018 | Lendlease | &²µ³Ù;£1²ú²Ô |
Ground Investigation Core & Sample Storage Facility | Q1 2016 | ALS Petrophysics | &±ô³Ù;£5³¾ |
Ground Investigation Works Framework Agreement | Q1 2015 | • Bam Ritchies • Environmental Scientifics Group • Fugro Seacore • Soil Engineering Geoservices • Structural Soils • Allied Exploration & Geotechnics • Farmer Associates • RPS Planning and Development • WYG |
£50³¾ - £100m |
HS2 Phase One Stations: Construction Partner (Euston) | Q1 2019 | Mace and Dragados | £1.5²ú²Ô |
HS2 Phase One Stations: Construction Partner Contracts (Old Oak Common) | Q3 2019 | Balfour Beatty, Vinci and Systra | £1.1²ú²Ô |
Party Wall Award Services for the Vezey Wing of the National Temperance Hospital | Q2 2016 | Lambert Smith Hampton | &±ô³Ù;£2³¾ |
Phase One Stations Professional Services Design Contracts (Birmingham Curzon Street Station) | Q1 2018 | WSP | £18m - £30m |
Phase One Stations Professional Services Design Contracts (Birmingham Interchange Station) | Q1 2018 | Arup | £13- £23m |
Phase One Stations Professional Services Design Contracts (London Euston Station) | Q1 2018 | Arup | £87- £98m |
Phase One Stations Professional Services Design Contracts (London Old Oak Common Station) | Q1 2018 | WSP | £47m - £70m |
Phase One: Plant Material | Q4 2016 | W Crowder & Sons | £5m - £9m |
Phase Two Development Partner | Q4 2016 | Bechtel | £130m - £170m |
Phase Two Professional Services Consultants - Civils design and environmental services | Q1 2017 | Lot 1 • Mott MacDonald with WSP Lot 2 • Aecom with Capita & Ingenieria y Economia Lot 3 • Arup |
£280³¾-£350³¾ |
Procurement of routewide provision of Specialist Security Services | Q4 2017 | Control Risks | £32³¾-42³¾ |
Railway Systems Design Services Framework | Q4 2015 | WSP | TBC |
Site Access, Land Referencing and Landowner Engagement Framework: Work Package (Phase 2a - West Midlands to Crewe) |
Q4 2015 | Mouchel, Arup, Aecom, WSP | TBC |
No comments yet