Construction manager has issued Galliford Try with non-completion notice for final phase of project

Athletes鈥 village construction manager Lend Lease has issued contractor Galliford Try with a non-completion notice for the last phase of the 拢700m London 2012 project.

In a letter seen by 黑洞社区 dated Monday (5 December) sent by Galliford Try to one of its subcontractors on the scheme, the contractor claims Lend Lease has made a 鈥渃lear statement鈥 it will pursue damages from the firm arising from the alleged non-completion.

Galliford Try is constructing the final two plots of the village, N13 and N26, which together are worth 拢80m and represent 14 blocks and 423 units according to construction data company Barbour ABI.

Sources close to the project confirmed the original deadline for Lend Lease to hand over the flats to the Olympic Delivery Authority (ODA) had been postponed from 31 October to 12 December. It is understood the revised deadline will be met.

The news came as the ODA again trumpeted progress on the scheme and gave media tours of some of the complete but unfurnished apartment blocks.
Qatari Diar and Delancey, the owners of the athletes鈥 village after the Games, also announced this week that the 2,800-home complex will be re-named 鈥淓ast Village鈥 and will be home to 6,000 people from 2013.

A spokesperson for the ODA said: 鈥淭he Olympic village remains on track to be completed and transferred to the London Organising Committee in January. It is not for the ODA to comment on commercial matters between contractors and their subcontractors.鈥

In its letter, Galliford Try stated its intention 鈥渢o recover and deduct鈥 monies from the subcontractor arising from its alleged failure to complete subcontract works and other alleged 鈥渟nags and defects鈥.

黑洞社区 reported in October that Galliford Try was in talks with three of its subcontractors - Prater, MPG and Reddington - over financial disputes arising from delays on the project. None of Galliford Try鈥檚 subcontractors were available for comment.

Galliford Try and Lend Lease referred 黑洞社区鈥檚 enquiries to the ODA.

  • A huge increase in security for the Olympics means the 拢9.3bn project is still in danger of busting its budget, the National Audit Office announced on Tuesday. However, the NAO reported continued good progress on the construction side, with the ODA on course to save more than 11% on the original 拢8.1bn build budget.