It鈥檚 been a year since London got the job of hosting the 2012 Olympics, and to the untrained eye, nothing much seems to have happened. Mark Leftly commentates on what鈥檚 been going on, and what鈥檚 planned for the next six years and three weeks
This week marks the first anniversary of London winning the right to host the 2012 Olympic Games. On that balmy summer鈥檚 day, Tony Winterbottom, director of the London Development Agency, told 黑洞社区 from the announcement ceremony in Singapore: 鈥淲hat happens next? We鈥檙e going to deliver the Olympic Games.鈥
Well, that was the intention. There are now six years and three weeks until the opening ceremony and little construction work has actually been done as land assembly and remediation have been the initial concerns. Also the masterplan has been revamped, the procurement methods have been argued over, and the whole programme is still at square one after eight months spent thinking it through. So here is 黑洞社区鈥檚 guide to where the London 2012 Games is currently at.
The organisational structure
The Olympic Delivery Authority is charged with building the venues and infrastructure for the Games. Last year, it appointed former Lend Lease boss David Higgins as chief executive and and American construction veteran Jack Lemley as chairman. Last month this was followed by other senior appointments. Howard Shiplee, who delivered the Ascot redevelopment became construction director; the Labour party鈥檚 former PR guru Godric Smith was named director of communications; David Wright, a former Arup director, was appointed director of infrastructure and utilities. Head of safety went to Lawrence Waterman, the pioneer of the occupational health scheme Constructing Better Health. Construction is represented by Sir Peter Mason, the outgoing Amec chief executive who will join in October. The full ODA executive team will be announced by the end of this month.
The contracts
The first contract to be let was the 拢200m scheme to bury 50 power lines across the Olympic site in Stratford, east London. This went to contractor J Murphy & Sons and French energy company EDF in September; its project director, the LDA鈥檚 Winterbottom, says that most of the project will be complete by 2008 鈥 鈥渋t鈥檚 going very well鈥.
Last month, Nuttall and Galliford Try were appointed as the remediation and demolition contractors for the Olympic park. However, other awards have been delayed as Higgins has revamped the entire construction programme. He decided to effectively subcontract much of the client role to an 鈥渄elivery partner鈥, which will be selected in August. There are currently four teams bidding for the role 鈥 Bechtel, an Amec and Balfour Beatty-led team, a Laing O鈥橰ourke consortium, and a team including Bovis Lend Lease and Halliburton subsidiary KBR. It is expected that all four will be invited to submit final bids later this month, following a process of competitive dialogue.
The programme
Higgins says a more detailed programme with project start and completion dates will be revealed this month, but what is known for sure is that construction work will not start in earnest until 2007, when most of the power lines have been completed. Transport work will start early next year in preparation for delivering the materials to site, as well as the rail improvements necessary for getting an estimated 200,000 people an hour on site.
A five member legal panel has already been appointed. This includes lawyers from Berwin Leighton Paisner, Clifford Chance and Pinsent Masons, and they will advise on procurement. The procurement methods chosen should be announced ahead of the Olympic stadium contract, which comes to the market later this summer. Other upcoming key dates include:
- September 2006:the Olympic transport plan will be made available for public consultation
- Late 2006: Procurement of the Zaha Hadid-designed aquatics centre begins
- January 2007: A new planning application will be submitted for the redesigned masterplan for the Olympic park. All land is due to be under ODA control by this stage; it currently owns 92-93% of the land it needs.
There has been speculation about increases to the price of the Games. It has been leaked that the infrastructure cost is 拢3bn, up from an initial estimate of 拢1bn, and private investment is likely to be needed to plug the shortfall. One model under consideration is the Milton Keynes鈥 鈥渞oof tax鈥, a tariff on developers to provide vital infrastructure.
Cost consultant EC Harris has estimated that the construction workload will be 拢2-2.8bn, adding 1.5-2% to the workload of the South-east each year between 2007 and 2012. Labour shortages are likely to be the key problem when addressing this increase; 150,000 jobs are likely to be created in the next seven years, a good proportion of which will be in construction. According to
EC Harris, all of this is likely to mean an inflation in tender price in London and the South-east of 5.5-6% over the next five years.
A Davis Langdon study in March warned that there would be price spikes in 2007/8 and 2010 as projects are built, and also that the Games would be a drain on skilled personnel and labour.
Legacy
鈥淚n February we decided to review everything on the site from a legacy perspective,鈥 says Higgins. It followed on from his decision the previous month to scrap the contracts that were already out for the velodrome construction and the Olympic programme manager role. The latter was replaced by the delivery partner role. These decisions set the Olympics back, but most industry figures have argued that any concerns have been exaggerated 鈥 eight months in a six-year programme should not matter, so long as the whole construction process has been improved.
Legacy was arguably the main reason for the rethink, and has even led to suggestions from Lord Coe that the 80,000-seat main stadium could become a ground for a premiership football club after 2012. It has also led to the appointment of some heavyweight regeneration players to the ODA board, including Manchester council chief executive Sir Howard Bernstein and Neale Coleman, Ken Livingstone鈥檚 policy adviser.
The changes to the masterplan have also been intended to reduce the possibility of the Games leaving white elephants. For example, the press and broadcast centres have been moved into the heart of the 300 ha site, so that rather than be knocked down as originally planned, they will provide 1 million ft虏 of office space after the Games.
Construction commitments
On Monday this week, the Strategic Forum got the DTI, the Treasury, the ODA, the London Organising Committee of the Olympic Games, the Department for Culture, Media and Sport, the Office of Government Commerce and the Greater London Authority to sign up to its Charter of construction commitments for the Games.
The document commits the public bodies to several targets in six key areas:
- Client leadership. Commitments include establishing a detailed brief with clear financial objectives.
- Procurement and integration. Commitments include procurement decisions to be made on best value rather than lowest cost and ensuring cash flow for suppliers, such as payment within 30 days.
- Design quality. Commitments include designs to be tested by third-party review panels.
- Sustainability. Commitments include developing an overarching sustainable development strategy and instigating plans to protect the local environment.
- Commitment to people. Examples include: establishing local employment projects and guaranteeing apprenticeship.
- Health and safety. Commitments include all 2012 Games construction projects to be injury-free; companies to sign up to the Strategic Forum鈥檚 health鈥檚 and safety code; all staff to hold CSCS cards or equivalent.
Timeline
2006
This week: Olympic construction commitments agreed and signed
July 2006: Public consultation on legacy plans; delivery programme outlined; procurement strategy announced and health and safety regime published
August 2006: Olympic delivery partner selected
Late summer 2006: Procurement process for the main stadium starts
September 2006: Olympic transport plan goes to public consultation
2007
January 2007: Planning application submitted for the new masterplan
Main construction work starts
2008
Burial of power lines completed
2011
Main construction work ends
27.07.2012
Opening ceremony of London 2012