Why is Hinkley delayed and overbudget?

Hinkley Point C

  • Project: Hinkley Point C
  • Started: December 2018
  • Finished: Target for first reactor 鈥 December 2025

What happened: In 2012 EDF estimated the cost to build Hinkley as 拢12bn, way above the government鈥檚 2008 estimate of 拢4bn. This grew incrementally to the most recent announcement that costs will now be 拢21.5bn-拢22.5bn. It said the risk of a delay of 15 months to construction of the first reactor and nine months to the second had increased.

What鈥檚 the groundwork problem?

The earthworks at Hinkley Point C required excavation of 2.3 million m3 of mudstone with limestone bands, to depths of up to 34m on a site the size of 240 football pitches. Sprayed concrete, strengthened by an estimated 112,000m of ground nails, was used to retain the excavated slopes. 

An EDF spokesperson said that ground investigation before starting showed 鈥渨eathered rock in places, with a number of faults.鈥 As work progressed, 鈥渋t became apparent that the extent of the faulted zones was more extensive than envisaged. 

鈥淚n addition, the areas of highly weathered rock degraded quickly, despite tight controls in terms of the maximum duration it could be exposed prior to blinding with concrete. These issues have led to additional excavation, additional ground nailing and additional substitution/replacement concrete.鈥

Other late nuclear projects

Project name: Olkiluoto

  • Started: July 2005
  • Finished: Expected July 2020
  • What happened: Originally scheduled to open in 2010, the 1.8GW reactor project suffered serious delays. Reactor designer Areva built the scheme on a 鈧3bn fixed price, leading to work stopping while a legal battle was fought over liability for costs. Areva said in 2012 full costs would be more than 鈧8bn.

Project name: Flamanville

  • Started: December 2007
  • Finished: Expected end of 2022
  • What happened: Problems with the 鈧3.3bn reactor project surfaced as early as 2008 with concrete quality issues. Faults in the pressure vessels identified later caused significant delays. Most recently, cooling circuit welds were judged not to be up to standard, and the final price will be at least three times the 鈧3.3bn estimate.

Project name: Taishan 1&2

  • Started: October 2009
  • Finished: Unit 1 鈥 December 2018, Unit 2 鈥 September 2019
  • What happened: Construction of the two 1.7GW reactors was supposed to take just 46 months, but ended up more than double that after reported problems. Both reactors are now in operation.