If an adjudicator fails to decide who owes who what money, you鈥檒l still have to pay up for all the refereeing they鈥檝e done

Well done PC Harrington. Well done because it had the courage to run a point in the High Court about adjudication that has been hanging around for the 13 years since it was invented. Harrington lost but it was a question worth asking. Let me tell you the story.

The adjudicator missed the underlying task to decide who owes who what money. That鈥檚 a big question running in his authority beyond the words on the notice

Wembley stadium contractor Multiplex sub-let reinforcement work to Harrington. The labour element became a sub-sub contract with Tyroddy Construction. Then Tyroddy and Harrington fell out. An adjudicator came onto the pitch. Modest, perhaps tiddler-size amounts of money were in dispute about Tyroddy鈥檚 retention release. Harrington opened its batting by informing the adjudicator he had no right to adjudicate because no dispute had arisen yet. Won鈥檛 do, said the adjudicator, and pressed on. Harrington then bowled up a defence, which said Tyroddy was overpaid on Wembley. In which case there was no claim for any money - and for good measure it counterclaimed for the so-called overpayment. So, said Harrington, Mr Adjudicator is obliged by this defence to decide the Tyroddy final account so as to fathom the alleged overpayment and any retention release and who pays what. Do you see how this adjudication has grown arms and legs? Tyroddy has simply asked for its retention in the formal notice of adjudication. But Harrington has exploded the affair into a strip down of the account. This was too much for the adjudicator. He said it was too far to say that his authority to decide retention release took him into this counterclaim. He was wrong. You can鈥檛 fathom one without the other. Harrington鈥檚 efforts to persuade the adjudicator to look at the sums due and paid and overpaid came to nought. So, his award didn鈥檛 take into account the counterclaim about over payment. Harrington said that was his mistake and no real adjudication had taken place. Mind you, it was always open to Harrington to run its own adjudication claiming overpayment. And if that proves to be the case the two separate awards can be conjoined for a net result. Be that as it may, the adjudicator had gone adrift by not bringing in the counterclaim and the court would not enforce.

That is just the beginning. The next bit 鈥渋s interesting and important鈥, said the High Court judge. Given that the adjudication is ineffective and a waste of time, isn鈥檛 it fair to say that no adjudication was carried out and that the adjudicator has not earned his salt? That鈥檚 the point run by Harrington in court. It argued there was 鈥渁 complete failure of consideration鈥 by the adjudicator. It鈥檚 a phrase used in failed contracts when there has been a failure of performance for which the other party has bargained. Given the adjudicator is in contract with Harrington and Tyroddy and given the award was useless, hey-ho, no fees?

Given that the adjudicator is in contract and given the award was useless, hey-ho, no fees?

The argument didn鈥檛 get home. The judge insists that the adjudicator is to be paid his full fee and insists that Harrington is liable just as is Tyroddy. That will come as a relief to adjudicators. It is first of all plain that the adjudicator鈥檚 rejection of the counterclaim as part of the dispute is not done in bad faith.

It is simply a mistake as to powers. An easy mistake; he thought it was stretching the adjudication too far, going where he ought not tread. He confined himself to what was said to be his task in the 鈥淣otice of Adjudication鈥. What he missed was that the underlying task was to decide who owes who what money. That鈥檚 a big question running in his authority behind the words on the face of the notice.

Harrington argued that there was a total failure of consideration by the adjudicator but that means complete failure. A contract 鈥渢o adjudicate鈥 contains a raft of services, or at least more than one. If some of the services have been provided there is no total failure. So, what is the bargained-for performance? Well, it鈥檚 a a lot more than 鈥渏ust鈥 the end decision. Loads of time is spent reviewing the documentation, then response, then more besides; to say nothing of the quarrels that arise. The adjudicator is employed not merely to produce a decision; he is there to operate as best he can a statutory contract especially for commercial construction. All he has to do is his honest best. Moreover, it is long since recognised that mistakes are inevitable. So Harrington and Tyroddy got precisely what they bargained for. Part of the adjudicator鈥檚 performance was as per his contract. So, there can鈥檛 be a total failure of consideration. Not in this case at least.

legal

Source: Simone Lea

Tony Bingham is a barrister and arbitrator at 3 Paper 黑洞社区s Temple. To read more articles by Tony,

Topics