In converting a 1930s police station into the Metropolitan Police鈥檚 new HQ, contractor Bam faced a difficult case. But noise reduction criteria, a cramped site and a high level of security were no match for Bam鈥檚 trusty team

Scotland Yard

鈥楤etter call in Curtis Green鈥 is not a familiar phrase. For decades, in popular fiction and common conversation, London鈥檚 police force has been referred to simply as 鈥淪cotland Yard鈥. Fortunately, after London鈥檚 mayor sold the Metropolitan Police鈥檚 New Scotland Yard home to developers, it was agreed that its replacement would keep the well-known name.

Part of the capital released by the sale is being used to fund the conversion of the former Whitehall Police Station, known as the Curtis Green 黑洞社区, into the Met鈥檚 new home.

The 拢58m conversion, designed by Stirling prize-winning architect Allford Hall Monaghan Morris (AHMM), will transform the 1930s police station into a headquarters building fit for a 21st-century police force. AHMM鈥檚 competition-winning scheme includes the addition of a transparent public entrance pavilion at the front of the building, a glazed rooftop pavilion and a large full-height extension to the rear.

It is a complex project made all the more challenging by an immovable completion date of 31 October 2016. 鈥淲e have a backstop date by which time the Met has to be out of the current New Scotland Yard building, which means that Bam has had to condense the design and overall construction programme to meet that deadline,鈥 says Gavin Pantlin, project manager for the Curtis Green 黑洞社区 for main contractor Bam.

In a tight spot

Its task has been made all the more demanding by the site鈥檚 location in the heart of Whitehall, which placed restrictions on when noisy construction tasks could be carried out and required Bam to maintain a highly secure construction site. Security is intense, not just because the building will be home to the Met Police鈥檚 headquarters functions but also because of the project鈥檚 neighbours: to the south the site borders the Norman Shaw North building, home to parliamentary offices; to the immediate west is Richmond House, occupied by the Department of Health; while to the north is the Ministry of Defence鈥檚 main building.

To enter the tightly-hoarded site on London鈥檚 Victoria Embankment, each of the 250 operatives has to have a fingerprint scan. Next to the entry turnstile is a hand-shaped outline onto which each worker places their right hand, palm-down: one, two, three, four, five - the scanner鈥檚 red LEDs turn green around each of the fingers when the scanner matches their prints to those on record. Only when all of the LEDs have turned green does the turnstile grant them access.

Scotland Yard

The site entrance disgorges operatives directly outside of the new oval-shaped, glazed entrance pavilion. This has been constructed in front of the Curtis Green 黑洞社区. The pavilion is perhaps the most obvious architectural manifestation of the Met鈥檚 desire to present a new, progressive and transparent face to the community it serves.

The pavilion鈥檚 curved glass walls are formed from a series of huge 3.5m x 2.4m double-glazed units, each weighing up to 900kg. As with much of this conversion, the entrance pavilion has been designed with physical security and operability in mind.

From the glazed entrance pavilion, visitors pass through into a newly created double-height lobby to enter the Curtis Green 黑洞社区 itself. The lobby is surrounded by meeting and function rooms on both the ground and first floors. Above this are six floors of open-plan offices on top of which sits a new rooftop pavilion.

The transparency theme from the entrance pavilion is continued inside the building; here Bam has punched a giant hole through the middle of the building鈥檚 reinforced concrete floor plates to open up the centre of the building. This glass-enclosed void now houses four scenic lifts that will transport workers between floors and up to the rooftop pavilion with its views out over the River Thames to the east and Downing Street to the west. The rooftop pavilion is intended to serve as a function room for the Met.

Investigation

It is a complicated conversion; to get the project to this stage in two years, Bam has had to focus hard on maximising construction efficiency.

The contractor won the design and build turnkey contract through competitive tender in December 2013. At the time of Bam鈥檚 appointment the design was still being developed and the scheme had yet to go to the planners. Bam exploited the opportunity afforded by its early appointment to offer construction and buildability advice to the design team of AHMM and engineer Arup under a pre-construction services agreement.

鈥淥ne of the big advantages of being involved at RIBA Stage 2 was in enabling Bam to influence the design to get the fastest construction programme,鈥 says Pantlin.

It was six months after Bam鈥檚 appointment that the planners gave the scheme the green light. Critically, from Bam鈥檚 perspective, planning permission included a requirement that the contractor adhere to strict construction noise criteria. 鈥淲e only found out about the noise constraints after we鈥檇 committed to meeting the October 2016 deadline,鈥 Pantlin says.

Scotland Yard

The Met鈥檚 new HQ is being created in the former 1930s Whitehall Police Station

Scotland Yard

Visualisations showing how the building will look when complete. View down to the entrance from inside the building

Raising the roof

Unusually, because there are no residents within earshot of the site, the planners required Bam to undertake its noisy operations early in the morning, between 6am and 9am, and in the evening between 6pm and 9pm. 鈥淗aving MPs as neighbours meant that we couldn鈥檛 make any noise during the day,鈥 says Pantlin.

One of Bam鈥檚 first construction tasks was also its most noisy: demolition of the building鈥檚 rear facade, removal of the roof, all staircases and lift shafts and opening up the floor plates. It was a task made all the more challenging by the Curtis Green 黑洞社区 having been designed and built in the run-up to the Second World War, which meant that it had a heavy-gauge, riveted steel structure that was encased in concrete and that had been designed to prevent progressive collapse in the event of bomb damage. 鈥淚t was a very robust structure to cut and carve,鈥 says Pantlin, tactfully. 

To ensure its neighbours were undisturbed during the works, Bam had consultant Arup carry out predictive noise mapping for all the demolition and construction tasks. It also took the precaution of fitting an acoustic screen to the protective scaffold adjacent to parliamentary offices. 鈥淭here was a lot of liaison with the neighbours to explain what works will be taking place, when and the noise levels that they could expect,鈥 Pantlin says.

Bam used Brokk robotic demolition equipment and to use what Pantlin describes as 鈥渕unching quiet鈥 techniques for most of the demolition. As demolition progressed down through the building, the contractor seized the opportunity to compress the construction programme further by constructing new risers and service shafts as this phase of the works neared its close.

The contractor also took the opportunity to fully survey what remained of the building structure. It was helped by the Met鈥檚 crime reconstruction team who, conveniently, happened to be experts in carrying out point cloud 3D surveys. The gathered data was fed into the project BIM model and the project used PAS 1192-5:2015 specification for security-minded modelling, digital built environments and smart asset management to ensure secure information sharing arrangements were in place for the BIM model.

Scotland Yard

Visualisations showing how the building will look when complete. The new entrance pavilion

Scotland Yard

Visualisations showing how the building will look when complete. A typical office floor

Crime reconstruction

Once the rear facade had been demolished, Bam set about erecting the new steel structure at the rear of the building. The original Curtis Green 黑洞社区 was C-shaped in plan, formed from a narrow rectangular floor plate flanked by two short wings. With AHMM鈥檚 design, the new steel structure infills the centre of the C to create larger rectangular floor plates; the structure also gives the modified building stability.

The new steelwork is supported on eight 750mm-diameter piles bored 32m into the ground in the small courtyard at the rear of the building. In addition, a further 30 piles, 350mm in diameter, were installed at the front of the building to support the new entrance pavilion.

With the piles installed, the site鈥檚 tower crane could finally be erected at the front of the building. The crane was essential in enabling the new steel structure to be constructed at the rear of the building. The new structure was built from steel sections that were no heavier than 7.5 tonnes. 鈥淚t was all blind lifting. The entire structure had to be designed to be craned in over the building,鈥 Pantlin says.

Scotland Yard

Diagram showing how new elements are being blended into the existing structure

Erection of the steelwork commenced in April 2015 and was finished by December that year. This included construction of a new top floor of offices, which the architect had slotted in behind the existing facade, and the addition of the rooftop pavilion above. 鈥淕etting erection of the structure completed on time was key to staying on programme,鈥 says Pantlin.

As the steel erectors raced the structure upwards they were closely followed by the cladding installers. AHMM selected a brightly coloured aluminium cladding system for the new rear facade, the colours of which were drawn from the surrounding streetscape. Once again, buildability issues influenced the choice of construction solution: 鈥淚t鈥檚 a unitised system because it was quickest to install,鈥 says Pantlin.

Protected from the weather by the cladding, fit-out of the new floor plates could commence. To maximise the floor-to-ceiling heights of the office floors, which are lower than would be in a conventional new-build office, a 350mm high raised access floor is used as a plenum to both supply conditioned air to the floors and as a cable distribution void. 鈥淚t is a similar cabling arrangement to a dealer floor - all cabling is underfloor, which required careful coordination鈥 says Roger Harding, director of real estate development for the Metropolitan Police.

BIM has been used to model all the building services, including the basement plantrooms, which the Met had point-cloud surveyed. 鈥淏IM was useful in helping to understand sequencing and access, particularly for large items of plant,鈥 says Pantlin. He says the BIM model is 鈥渘ot fully data-rich鈥, but the information within the model is to a 鈥渇airly high level鈥.

Despite all this complexity, the project has progressed as planned and, with just four months remaining until the Met take up residence, Pantlin says the project is on schedule for an October handover. The building services are being installed on the office floors by Bam and its subcontractors. Bam鈥檚 FM team will also be involved after handover when a form of Soft Landings post-occupancy evaluation will be used to ensure the building services operation is optimised once the Met have taken up residence which, if the project continues on programme, should be very soon. Step forward, Dixon of Curtis Green.

Scotland Yard

With the completion date two months away the works are nearly finished

Scotland Yard

With the completion date two months away the works are nearly finished


Project team

Client London Mayor鈥檚 Office for Policing and Crime
Main contractor Bam
Architect AHMM
QS and client鈥檚 project manager Arcadis
Structural and MEP engineer Arup