- News
All the latest updates on building safety reformRegulations latest
- Focus
- Comment
- Programmes
- CPD
- ºÚ¶´ÉçÇø the Future
- Data
2024 events calendar
ºÚ¶´ÉçÇø Awards
Keep up to date
- ºÚ¶´ÉçÇø Boardroom
All the latest updates on building safety reform
2024 events calendar
ºÚ¶´ÉçÇø Awards
Keep up to dateInformation gathering | 6 weeks |
Invasive site trail holes | 20 weeks |
Determination of impacts and collation of C3 and C4 quotations | 14 weeks for each |
Arrangement of new service connections | 25 weeks |
Abandonment of existing assets | 13 weeks |
Preparation to construct minor works | 5 weeks |
Preparation to construct major works | 13 weeks |
Construction and commissioning of minor works | 6 weeks |
Construction and commissioning of major works | Several months |
Site powered by