Research laboratory cost breakdown |
| element cost | cost/m² gfa £ | % of total cost |
Substructure | 842 000 | 76.55 | 4.71 |
Ground slab; 200 mm thick reinforced insitu concrete bed, hardcore; damp-proof membrane; reinforced concrete pad and perimeter foundations | | 4500 m2 Ìý | @ £110 |
Extra over for basement construction | | 400 m2 Ìý | @ £280 |
Allowance for below-ground drainage and incoming services | | Ìý45m2 | @ £50 |
Extra over for sump chamber and pump installation | | | Item @ £10 000 |
Frame | 877 900 | 79.81 | 4.91 |
Insitu concrete frame; comprising 250 mm thick shear walls and rectangular and circular columns | | 5900 m2 Ìý | @ £30 |
Structural steel framing to roof level plant rooms including roof purlins; (average rate for universal and hollow sections) | | 235 tonnes Ìý | @ £1300 |
Extra over for structural steel framing to external service ducts | | 85 tonnes Ìý | @ £840 |
Timber roof structure, glu-lam beams, ply box beams; structural steel connections | | 1800 m2 Ìý | @ £180 |
Upper floors | 626 000 | 56.91 | 3.50 |
Insitu concrete troughed floor slabs; 650 mm thick overall | | 3600 m2 | @ £110 |
Insitu concrete flat slabs; average 300 mm thick | | 2300 m2 Ìý | @ £100 |
Roof | 597 800 | 54.35 | 3.35 |
Roof cladding; raised-seam terne-coated stainless steel sheet cladding, inner tray, insulation, vapour barrier, plywood base | | 5570 m2 Ìý | @ £70 |
Extra over for ridges, edge trims, cappings and gutters | | 5570 m2 Ìý | @ £10 |
Rooflights; double-glazed units; polyester powder-coated aluminium frame; including allowance for opening lights | | 240 m2 Ìý | @ £500 |
Allowance for roof safety system | | 460 m Ìý | @ £70 |
Stairs | 251 000 | 22.82 | 1.40 |
Insitu concrete stairs and half landings; screed to treads and risers | | 58 m Ìý | @ £500 |
Allowance for balustrades and handrails to staircases; stainless steel with glazed panels to feature stairs, powder-coated mild steel to others; timber handrails | | | Item @ £100 000 |
Allowance for balustrades and handrails to access bridges; stainless steel with glazed panels to feature bridge, powder-coated mild steel to others; timber handrails | | | Item @ £30 000 |
Allowance for timber handrails to reception area; including glazed panels | | | Item @ £17 000 |
External escape staircases; spiral; galvanised mild steel; 2.1m diameter, 9 m high; including access gantries | | 6 Ìý | @ £12 500 |
External walls, windows and doors | 1 594 000 | 144.91 | 8.92 |
Facing brickwork cavity walls; handmade facings, insulation and blockwork; windposts | | 3075 m2 Ìý | @ £130 |
Wall cladding; raised-seam terne-coated stainless steel sheet cladding, underlay; insulation; plywood base | | 2900 m2 Ìý | @ £110 |
Curtain walling; aluminium-framed, sealed double-glazed units; low E glass to inner pane; including structural steel secondary support | | 820 m2 Ìý | @ £300 |
Extra for glazed double doorsets; ironmongery and accessories | | 12 Ìý | @ £3000 |
Extra for revolving entrance doors; ironmongery and accessories | | 1Ìý | @ £18 000 |
Structural glazing; double-glazed units; including structural steel secondary support | | 115 m2 | @ £600 |
Windows; sealed double-glazed units in polyester powder-coated steel frames | | 830 m2 Ìý | @ £220 |
Doors and frames; part-glazed; polyester powder-coated steel; ironmongery | | 36Ìý | @ £2500 |
Doors and frames; part-glazed; hardwood; ironmongery | | 38Ìý | @ £1000 |
Louvre panels to plant areas; stainless steel | | 520 m2 | @ £330 |
Sunshading; perforated louvre cassettes | | 185 m Ìý | @ £130 |
Internal walls and partitions | 619 600 | 56.33 | 3.47 |
Blockwork partitions; 100 mm and 140 mm thick; head restraint (average rate) | | 3700 m2 Ìý | @ £36 |
Part-glazed partitions; non-fire rated; powder-coated steel frame; single-glazed lights; plasterboard lining both sides; doors; ironmongery (average rate) | | 1470 m2 Ìý | @ £210 |
Part-glazed partitions; fire rated; powder-coated steel frame; single-glazed lights; plasterboard lining both sides; doors; ironmongery (average rate) | | 290 m2 Ìý | @ £330 |
Metal stud partitions; 2 layers wallboard each side; insulation | | 150 m2 Ìý | @ £40 |
Toilet cubicle partitions and backpanels | | 26 Ìý | @ £1200 |
Shower cubicle partitions and backpanels | | 2Ìý | @ £2400 |
Internal doors | 222 450 | 20.22 | 1.25 |
Flush doors; fire-rated; solid-core veneer-faced; hardwood frames; ironmongery; complete | | 107 Ìý | @ £700 |
Flush doors; fire-rated; solid-core laminate-faced; hardwood frames; ironmongery; complete | | 140 | @ £750 |
Flush doors; non-fire-rated; solid-core veneer-faced; hardwood frames; ironmongery; complete | | 74 Ìý | @ £575 |
Wall finishes | 181 070 | 16.46 | 1.01 |
Sand cement render; 13 mm thick | | 650 m2 Ìý | @ £10 |
Plaster; two coats, 13 mm thick | | 6875 m2 Ìý | @ £8 |
Extra for allowance for radiused internal and external angles to plasterwork in special lab areas (average rate) | | 580 m Ìý | @ £35 |
Two coats emulsion paint; to plaster or plasterboard | | 13 500 m2 Ìý | @ £3 |
Two coats woodstain; to timber | | 640 m2 Ìý | @ £8 |
Ceramic tiles; to sand cement backing or plasterboard | | 485 m2 Ìý | @ £50 |
Hygienic wall coverings; three coats acrylic polymer | | 940 m2 Ìý | @ £10 |
Hygienic finish to kitchen areas; laminate panels | | | Item @ £20 000 |
Floor finishes | 386 310 | 35.12 | 2.16 |
Sand cement screed; 75 mm thick; floated finish; including scabbling to floor slab | | 6800 m2 Ìý | @ £11 |
Raised access floor; 150 mm deep floor void; including allowances for cavity and acoustic barriers, services bridging and so on | | 1440 m2 Ìý | @ £37 |
Extra for 450 mm deep floor void | | 680 m2 | @ £6 |
Extra for bonded vinyl floor finish | | 45 m2 Ìý | @ £20 |
Heavy duty carpet tiles; to raised floor tiles or screed | | 3500 m2 Ìý | @ £30 |
Heavy duty vinyl; including smoothing compound and coved skirting | | 4400 m2 Ìý | @ £20 |
Softwood skirting; woodstain finish | | 1000 m Ìý | @ £10 |
Natural stone flooring; including allowances for screeds and skirtings; to reception area | | 350 m2 Ìý | @ £90 |
Epoxy resin floor finish to concrete floor slabs in plant rooms | | 2750 m2 Ìý | @ £5 |
Allowance for mats and matwells | | | Item @ £5 000 |
Ceiling finishes | 315 210 | 28.66 | 1.76 |
Suspended ceilings; metal tray; concealed grid | | 2600 m2 Ìý | @ £35 |
Extra for perforated tiles | | 2200 m2 Ìý | @ £3 |
Extra for acoustic treatment, absorbent pads | | 1350 m2 Ìý | @ £2 |
Suspended ceilings; mineral fibre acoustic plank; concealed grid | | 960 m2 Ìý | @ £43 |
Suspended ceilings; hygienic ceiling finish to kitchen; extruded PVCu | | 320 m2 Ìý | @ £34 |
Suspended ceilings; plasterboard on MF system; including access panels | | 120 m2 Ìý | @ £40 |
Extra for plasterboard in margin work to other suspended ceiling systems | | 220 m2 Ìý | @ £50 |
Plywood roof panels; vapour barrier and insulation | | 1100 m2 Ìý | @ £60 |
Intumescent clear finish; to plywood ceiling panels and exposed timber roof members | | 3150 m2 Ìý | @ £13 |
Furniture and fittings | 116 000 | 10.55 | 0.65 |
Reception desk | | | Item @ £20 000 |
Crash protection rails | | 630 m Ìý | @ £45 |
Vanity units; melamine-coated | | 15 m Ìý | @ £770 |
Allowance for cloakroom fittings, lockers and so on | | | Item @ £10 000 |
Allowance for teapoints in office areas. | | | Item @ £10 000 |
Allowance for shelving and so on | | | Item @ £10 000 |
Allowance for window boards | | | Item @ £7000 |
Window blinds | | 260 m2 Ìý | @ £35 |
Allowance for statutory signage | | | Item @ £5000 |
Allowance for directional signage | | | Item @ £5000 |
Sanitary fittings | 40 000 | 3.64 | 0.22 |
WCs, urinals, washhand basins; generally | | 75 Ìý | @ £400 |
Allowance for fittings for disabled WCs | | | Item @ £2000 |
Allowance for hand dryers | | | Item @ £8000 |
Services equipment | 1 382 600 | 125.69 | 7.74 |
Laboratory furniture installation; worktops, shelves and underbench units | | 3850 m2 Ìý | @ £80 |
Laboratory furniture installation; plumbing services and laboratory sinkwastes | | 3850 m2 Ìý | @ £30 |
Laboratory furniture installation; service outlets | | 3850 m2 Ìý | @ £10 |
Laboratory furniture installation; electrical installation | | 3850 m2 Ìý | @ £30 |
Laboratory fume cupboard installation; based on variable air-volume system | | 93 Ìý | @ £5000 |
Extra for non-standard fume cupboards (12 walk-in fume cupboards) | | | Item @ £22 000 |
Services installations and connections to fume cupboards; ductwork connections to extract system, plumbing and waste outlets, electrical services, fire protection | | 93Ìý | @ £1700 |
Laboratory cold room installation | | | Item @ £20 000 |
Kitchen installation complete; catering, storage and dishwash equipment | | | Item @ £70 000 |
Servery equipment | | | Item @ £70 000 |
Disposal installations | 187 800 | 17.07 | 1.05 |
Rainwater goods; steel downpipes | | 425 m Ìý | @ £60 |
Soil, waste and vent to landlord’s installation; PVCu pipework and fittings | | 11 000 m2 Ìý | @ £2 |
Soil, waste and vent to tenant’s installation; including kitchen installation and special wastes to laboratory areas | | 6100 m2 Ìý | @ £23 |
Water installations | 296 500 | 26.95 | 1.66 |
Hot and cold water service; calorifiers; hot and cold water storage; distribution | | 11 000 m2 Ìý | @ £2 |
Hot and cold water service to laboratory and kitchen/servery areas; calorifiers; hot and cold water storage; distribution | | 6100 m2 Ìý | @ £45 |
Space heating and air treatment | 3 083 300 | 280.30 | 17.26 |
Gas installation | | | Item @ £13 000 |
Low-temperature hot-water heating; boiler plant; stainless steel flues; pumps and valves; distribution within plant rooms; insulation | | 11 000 m2 Ìý | @ £30 |
Low-temperature hot-water heating; general distribution; pipework; insulation; radiant panels | | 11 000 m2 Ìý | @ £30 |
Chilled water installation; sized for laboratory cooling loads; chillers and heat rejection plant; pressurisation unit; pumps and valves; distribution within plant rooms; insulation and trace heating | | | Item @ £330 000 |
Supplementary chilled water installation; chillers and heat rejection plant; pressurisation unit; pumps and valves; distribution within plant rooms; insulation and trace heating . | | 7900 m2 Ìý | @ £17 |
Supply and extract ventilation; air-handling units; heating, cooling and reheat coils; ductwork in risers and plant rooms | | | Item @ £350 000 |
Air-conditioning; four-pipe fan-coil and variable-air-volume installations; chilled water distribution; condensate drainage; fan-coil units; ductwork; terminal units; insulation; grilles and diffusers | | 8850 m2 Ìý | @ £140 |
Extra for fume cupboard/safety cupboard extract system | | 3850 m2 Ìý | @ £80 |
Toilet extract installation | | | Item @ £26 000 |
Kitchen extract installation | | | Item @ £23 000 |
Electrical installations | 1 364 500 | 124.05 | 7.64 |
Allowance for HV switchgear and distribution | | | Item @ £30 000 |
Mains and sub-mains installation | | | Item @ £200 000 |
Small power distribution to laboratories | | 5750 m2 Ìý | @ £25 |
Small power distribution; busbar and floorbox to office areas, wall-mounted elsewhere | | 5250 m2 Ìý | @ £15 |
Lighting distribution and accessories | | 11 000 m2 Ìý | @ £25 |
Luminaires and lamps | | 11 000 m2 Ìý | @ £25 |
Emergency lighting installation | | 11 000 m2 Ìý | @ £8 |
Allowance for external lighting | | | Item @ £35 000 |
Power to mechanical services | | | Item @ £25 000 |
Containment; trunking, tray and ladder rack to laboratory areas | | 5750 m2 Ìý | @ £17 |
Containment; trunking, tray and ladder rack to office etc areas | | 5250 m2 Ìý | @ £5 |
Standby generator installation | | | Item @ £65 000 |
Landlord’s UPS installation | | | Item @ £25 000 |
Lift installations | 210 000 | 19.09 | 1.18 |
Glazed feature lifts; hydraulic; eight-person, serving two stops each | | 2 Ìý | @ £45 000 |
Extra for structural steel frame to feature lifts | | | Item @ £40 000 |
Passenger/goods lift; hydraulic; 21-person, 1600 kg; serving three stops | | | Item @ £50 000 |
Passenger/goods lift; hydraulic; 13-person, 1000 kg; serving two stops | | | Item @ £30 000 |
Protective installations | 79 000 | 7.18 | 0.44 |
Earthing and bonding | | 11 000 m2 Ìý | @ £4 |
Lightning protection | | 11 000 m2 Ìý | @ £2 |
Gaseous fire suppression system; to archive area | | | Item @ £13 000 |
Communications installations | 308 000 | 28.00 | 1.72 |
Fully addressable fire and smoke detection and alarm system | | 11 000 m2 Ìý | @ £18 |
Intruder detection | | 11 000 m2 Ìý | @ £5 |
CCTV installation | | | Item @ £35 000 |
Access control system | | | Item @ £20 000 |
Special installations | 660 000 | 60.00 | 3.69 |
ºÚ¶´ÉçÇø management system | | 11 000 m2 Ìý | @ £45 |
Medical gases installation | | | Item @ £90 000 |
Vacuum-pump system | | | Item @ £75 000 |
Compressed air installation | | | Item @ £60 000 |
Builder’s work in connection | 635 000 | 57.73 | 3.55 |
Additional structural steelwork to plant room | | | Item @ £60 000 |
Forming holes, chases etc; allow 7.5% | | | Item @ £575 000 |
Preliminaries and contingencies | 2 990 000 | 271.82 | 16.74 |
Construction manager’s fee, establishment and supervision; allow 15% | | | Item @ £2 240 000 |
Contingency sum; allow 5% | | | Item @ £750 000 |
Overall construction cost | 17 866 040 | 1 624.19 | 100.00 |
|