City鈥檚 MPs, including Alan Johnson, to urge fast-tracking of BSF programme after floods

The 黑洞社区 Schools for the Future (BSF) programme in Hull could be brought forward two years because of damage to the city鈥檚 schools in its recent floods.

Damage caused by recent floods

Initial consultations over a package worth 拢220m were launched last month but it is now understood that the money for it may be released early because of the damage to existing schools.

Stephen Brady, a Labour councillor, said John Prescott, Diana Johnson and Alan Johnson, the three MPs who represent the city, have told the council they will ask for the BSF projects to be fast-tracked.

Brady said: 鈥淲e鈥檝e got to make the schools habitable, and there鈥檚 no point in wasting money on temporary repairs when we鈥檝e got the BSF project just around the corner. Prescott said he wants to bring it forward now. It鈥檚 the perfect opportunity for it.鈥

Work on the BSF programme was supposed to begin in 2010 and end in 2015, but if approvals and procurement are rushed through, building could begin next year.

BSF declined to comment.

The funding would be particularly welcome as it is understood that many council buildings, including schools, are not insured for flood damage.

Hull suffered some of the worst of the regional flooding that hit Yorkshire and north-east England.

As many as one in four of the 5,000 flood-affected homes is thought to be uninsured, and the council has had to hire small contractors to help with repairs. As many of these firms are not on the council鈥檚 preferred list, unions have raised concerns over safety and general probity.

Ucatt said it was imperative that criminal checks were made. 鈥淭he workers are welcome, but safety measures still need to be applied and corners must not be cut,鈥 it said.

鈥 Scottish contractor Robertson has reached financial close on the 拢200m Newcastle BSF programme.

The firm will deliver the programme as part of a consortium with Sir Robert McAlpine and US firm Parsons Brinkerhoff. The construction of 15 schools is expected to complete in 2010.