Contract now 14 months late as audit office highlights 拢1bn-a-year shortfall in schools programme
The start of one of the biggest 黑洞社区 Schools for the Future contracts will be delayed by a further two months. The news comes as the government鈥檚 spending watchdog said the programme needed an extra 拢1bn a year to get back on track.
The latest delay in appointing a preferred bidder on the 拢350m Salford and Wigan BSF, which is already a year behind, comes amid continuing concern over the government鈥檚 reliance on PFI schemes to ease the recession.
A source close to the Salford PFI scheme, where Lend Lease and a Hochtief/Laing O鈥橰ourke joint venture are the remaining bidders, said it was likely that a preferred bidder would not be announced until March at the earliest. The appointment was originally due in January 2008, and was then expected last month after a series of delays.
The source said the delay was 鈥減robably more to do with procurement issues than finance鈥. However, it is thought that Salford and Wigan is one of the schemes considering applying for funding from the 拢300m set aside by the European Investment Bank to speed up schools schemes that have a PFI element.
The delay emerged as the National Audit Office (NAO) said the government needed to increase expenditure on the BSF programme from 拢2.5bn a year to between 拢3.4bn and 拢3.7bn from 2010-11 onwards if it is to address rising costs and complete all 3,500 new schools and refurbishments by 2020, its stated target.
The extent to which problems in the markets will affect BSF is still unclear
NAO report
The NAO鈥檚 report warns that 鈥渢he extent to which problems in the finance markets will affect BSF is still unclear鈥 and that rising construction costs will add 拢3bn to the programme.
The total cost of BSF has risen from 拢45bn to between 拢52bn and 拢55bn, with the bulk of the increase owing to the widened scope of the programme.
The report says the number of schools in procurement and construction at any time needs to double over the next three years in order to hit targets. It says no PFI deals were signed between October and the start of February.
Tim Burr, head of the NAO, said: 鈥淚t remains a challenge to deliver the 250 schools a year needed to include all schools by 2020.鈥
Schools minister Jim Knight said the report reflected the situation when the research was done six months ago but that some schools might not be finished by 2020.