Converting an existing building is often the best option for opening new hotels. Here are the main design considerations and costs

01 / INTRODUCTION

The development of new-build hotels in major city centres is increasingly constrained by the availability and cost of land. However, location is a key driver and major city centres continue to be first-choice destinations for hotel operators and brands.

One way to satisfy this demand is to look at the conversion of existing buildings, notably offices, to hotel use.

Hotel chains have recognised the importance of conversion projects in maintaining the growth of their brand portfolios in major city centres. Some major chains have developed or adapted brands that are considered suitable for conversion projects, bringing with them flexibility in the previously very rigid 鈥渂rand standards鈥. Brands such as Doubletree by Hilton, Hotel Indigo (IHG) and Pullman (Accor) have all seen a rapid increase in hotel openings in cities through the world.

In order to interpret the issues surrounding conversion, we must first examine the key issues affecting how hotels are designed.

To guests, a successful hotel means value for money, comfort, convenience, style and great service. For the hotel operator, a successful hotel has many satisfied repeat customers and a continued high reputation for excellence in the marketplace. For the developer, it means profitability and an asset of high value for years to come. For the design team, it鈥檚 another hotel project, successfully implemented.

As with all building types, the challenge is taking traditional cost drivers and design parameters that are well known and understood for new-build projects and applying them to the constraints of an existing building.

costmodel2

London鈥檚 Cumberland Hotel near Marble Arch contains over 1,000 rooms and a conference venue

02 / MAJOR COST DRIVERS

The major cost drivers of a hotel development may include:

New-build specific

  • Site location, shape, conditions, means of access and visibility
  • Position of the hotel in the development
  • The shape and form of the building
  • The storey height - if exceptionally high, it will need a heavier structure, more complex foundations, additional lifts and fire-fighting installations

Conversion

  • The external facades, particularly the extent of glazing and cladding
  • The level of sophistication of building services and fire-protection systems
  • Any particular requirements of the chosen hotel operator
  • Shape and layout of the guestrooms zone, particularly if this is a tower. In a high-rise building, a transfer lobby and high-speed lifts will be required
  • The level of provision and facilities of rooms
  • Location of function rooms. One major impact on the cost of the structure is the location of the main function room or ballroom. Normally, the ballroom is not directly below the hotel guestrooms tower, as it requires column-free space that would be difficult to accommodate without the introduction of extensive, and expensive, transfer structures at the base of the tower.

As we can see, while several major issues are fixed and beyond the scope of a conversion to change, many more require decisions that will be key to the success of the project.

Probably the most significant major consideration is the configuration of the guestrooms, particularly if this is in the form of a tower. Analysis shows that some shapes and configurations of a guestroom tower yield more cost-effective solutions than others. In fact, the choice of configuration can affect the efficiency by as much as 20% of the gross floor area.

Ideally, the efficiency of the guestroom zone should be in the region of 75% for a tightly designed, double-loaded corridor layout. However, for a single-loaded
corridor or atrium layout, the efficiency could drop to as low as 60%. Obviously, the higher the efficiency, the more economic the construction cost. It is critical to ensure the design is economical without sacrificing the design intent. Due to the multiplier effect of having many floors in the guestroom zone, minor differences or inefficiencies can have a major impact on the construction cost.

03 / TYPICAL GUESTROOM LAYOUT

To design a hotel floor without the constraints of working in an existing building, a range of different shapes would be available. Typically guestroom sizes are generally standardised across floors with an optimal bay system allowing different room and suite configurations. For a five-star hotel, rooms would be rectangular in shape, in the region of 40-50m虏 net area including sleeping area and bathroom. Some developers or designers might attempt to provide larger and odd-shaped rooms but these may not be economical.

Good workable dimensions would be approximately 4.5m x 9.1m. The width should not be excessive, as it would increase the length of the corridors, the cost of the structure and affect the external walls of the bedroom zone.

The offset configuration (below) is the most efficient in terms of accommodating more rooms per floor, with minimum effect on external walls and finishes. Efficiency is in the region of 75%.

The atrium configuration (below) is served by single-loaded corridors, which reduce efficiency. Though it may provide an opportunity for glass elevators, there is a cost premium. Smoke extraction and the extra cost of roof construction is a major consideration. Efficiency is likely to be about 60%.

It is within this context that the difficulties of converting an existing building to hotel must be reviewed.

costmodel5

04 / CONVERTING OFFICES TO HOTELS: KEY ISSUES

Space

The simplest form of conversion is of a rectangular office building into an economy, room-only hotel, avoiding long spans and difficult room shapes. However, this is also the least attractive option in terms of business case. Due to modern methods of construction for budget hotels, it is often far cheaper to create these from scratch either in empty sites or as part of mixed-use developments. Often, the stronger demand for conversion is within the context of architecturally interesting, sometimes listed original buildings, or where the development of a site requires the inclusion of additional functional requirements. If a new hotel is to be created within the restrictions of an existing floor plate, efficiency can rapidly be lost based on the arrangement of rooms and optimum bay widths within any given block of rooms.

When space planning within an existing building, the following factors must be considered:

  • Functional requirements of the hotel, particularly those requiring long spans such as conference and banquet facilities
  • Number of guestrooms per floor
  • Lift location and escape staircase cores
  • Shape of guestroom tower, as it affects the wall-to-floor ratios
  • Corridor configuration. The following table shows an example hotel area schedule, and demonstrates the greater area needed than for a typical new-build luxury hotel:
Functional areaOptimum luxury area (m2)Example luxury conversion area (m2)
Bedrooms 41.50 42.31
Bedroom circulation 41.50 13.91
Public areas 41.50 48.96
Back of house 20.79 28.55
  100.00 133.73

Services

The successful conversion of an office to a hotel relies on a good understanding of the opportunities and limitations of the office building and how this differs from the needs of a hotel. An office is arranged to maximise floor area and ceiling heights so the services risers will usually focus on a limited number of main risers. In contrast, a hotel needs distributed risers on its bedroom floors to cope with the distributed nature of the bathrooms. How these are integrated will be a key consideration.

For any function spaces, such as restaurants or conference rooms, the challenge is to minimise the impact of the bedroom risers and create, where possible, riser and column-free spaces. The base office should suit this better, although the volume of fresh air and extract required will be greater for the hotel, which will impact on ceiling heights and riser sizes.

costmodel3

One Aldwych hotel in Covent Garden is partly built on the site of a former office

The nature of the differing spaces for a hotel suggests a ventilation solution with a greater number and extent of air-handling systems than would be the case for a simple office. This may extend the roof plant areas. Similarly, greater water storage and boiler capacities will be required, which will impact on plant areas at low level.
Opportunities exist with elements such as the chillers, where reduced capacity may be required, and with sprinklers, as these may not be required in a hotel (dependent on operator and brand).

Acoustic separation between bedrooms is also important but an office building will not normally have sufficient floor-loading capacity to allow heavyweight dividing walls, so a lightweight acoustic stud wall will be required with care taken at the service penetrations. How these interface at the perimeter with the existing facade is a key detail.

With respect to utilities, an office building will usually have a greater electrical supply capacity than is required for a hotel due to its denser occupation, but the water supply capacity and the gas availability need to be checked early to ensure that any upgrades in supplies are carried out. The many additional bathrooms lead to much greater water consumption and gas is needed to generate the hot water.

Due to the consistent load in hot water there are greater opportunities for low and zero-carbon technologies such as combined heat and power, solar panels and ground source heat pumps. These can deliver savings in running costs and assist in demonstrating the green credentials of the building.

Structure

Structurally, the key to converting an office to hotel use is a good understanding of the existing building. The availability of the existing structural drawings for the office may allow the greatest opportunity to modify the structure with minimum risk.

Alteration of the structure to accommodate the new servicing provision and the architectural aspirations can prove problematic - as described above, the building services will require a new strategy to suit the hotel use. To achieve this there will be a need to cut through structure to achieve the new risers and service distribution. Some forms of floor construction lend themselves to adaptation more than others; again, a good understanding of the building form is essential to allow the efficient design of development concepts.

Floor loading capacity can be a key issue: recent office developments have often been designed with a relatively high loading allowance that allows a good level of 鈥渓oad trading鈥. Bedrooms have a lower live load requirement, thus 鈥渟pare鈥 load could be used for new finishes, partitioning or potentially to justify the inclusion of additional storeys on top of the existing building. In other office buildings, however, there may be limited loading allowances, so careful consideration would need to be given to the inclusion of features such as baths in bedrooms areas, pod construction for bathrooms, balconies and other specific features.

Solutions to allow the removal of columns to achieve open space within the front-of-house facilities such as restaurants, lounges and entrance spaces are essential. Structurally, the solutions need to consider the most appropriate way to transfer the upper floor loads, within the floor-to-floor space available. This may involve transferring load back into columns below or introducing new structure and foundations.

As stated above, incorporation of new lifts into the building massively affects the space planning. Key to achieving these new parts of the structure is working out where and how the floor structures can be cut to form the opening through the height of the building.

If the opportunity exists to increase the height of the building, consideration of the horizontal (wind) loading is as critical as the accommodation of the additional dead and live loading that the existing building will have to bear. Therefore, it is essential that the building stability should be established before designing the new floor plates.

New spa and pool facilities introduce a significant loading to the building and will necessitate significant new structure or strengthening to achieve their form as well as to accommodate the new servicing provision, finishes and associated facilities.

costmodel1

Capital&Centric is planning to turn Liverpool鈥檚 Littlewoods Pools 黑洞社区 into a hotel

 

What needs to go in? Typical hotel configuration by standard

Economy 2-3 starMid-market 3-4 starUpmarket 4-5 starLuxury 5 star plus
Bedrooms and restaurant or bar Bedrooms, restaurant and bar Bedrooms, restaurant, bar, conference and fitness Bedrooms, restaurant, bar, conference and fitness

 

05 / COST MODEL

The cost model is for the conversion of an existing office building into a 5-star luxury hotel with a gross internal area (GIA) of approximately 13,700m虏. Costs are at second quarter 2013 price levels, based on a lump sum contract in a south-east England location. The following items are excluded: operating supplies and equipment, mock ups, professional fees, client pre-opening costs, external works costs, one-off artworks or sculptures, site acquisition costs, finance costs and VAT.

The rates may need to be adjusted to account for specification, site conditions, procurement route and programme. For other locations, the costs may be adjusted by the following indicative multiplying factors:

Location factors

cost model

cost model

The St. Pancras Renaissance London hotel was converted back into a hotel after serving as offices and then lying empty for several decades

COST MODEL

 Total (拢)拢/尘2 
黑洞社区 clearance 1,470,000 107.30 3.73%
Stripping out and disposal of all loose fixtures, fittings, non-structural walls and partitions, redundant M&E services installations, floor, wall and ceiling finishes and general debris to leave a clean shell; 13,700m2 @ 拢100 1,370,000    
Allowance for identification and removal of asbestos (to be confirmed, subject to surveys); 1 item @ 拢100,000 100,000    
Substructure 502,000 36.64 1.27%
Allowance for breaking out basement slab in isolated areas for repairs and remedial works to substructure; 140m2 @ 拢300 42,000    
Allowance for underpinning and repairs to foundations; 1 item @ 拢200,000 200,000    
Formation of lift pit; 5 nr @ 拢5,000 25,000    
Allowance for waterproof concrete lining walls to basement and basement waterproofing; 750m2 @ 拢280 210,000    
Allowance for modifications and repairs to
under-slab drainage system; 1 item @ 拢25,000
25,000    
Frame and upper floors 686,000 50.07 1.74%
Allowance for strengthening and repairs to existing structure; 13,700m2 @ 拢20 274,000    
Alteration; removal of floor structure and columns between ground and first floor; installing transfer structures to open up public areas; 1 item @ 拢200,000 200,000    
Repairs, sundry infilling of openings in existing floors and re-screeding to accept new floor finishes (assessed at 40% of total area); 4,000m2 @ 拢40 160,000    
Form new openings through floors for service risers and other designed penetrations; 80 nr @ 拢650 52,000    
Roof 64,500 4.71 0.17%
Repairs to existing roof fabric including slatework, flashings, gutters and parapet walls, say 10%; 140m2 @ 拢175 24,500    
Allowance for roof level ancillaries; walkways, sundry plant supports and bases; 1 item @ 拢30,000 30,000    
Installation of fall arrest system and safety balustrades and handrails; 1 item @ 拢10,000 10,000    
Stairs 268,000 19.56 0.68%
New in-situ concrete main staircase; ground to fifth floor including handrails, floor and soffit finishes and nosings; 1 item @ 拢150,000 150,000    
Repairs and upgrading to existing concrete staircase to form front-of-house stair, including balustrades, handrails and finishes (rate per flight); 10 nr @ 拢10,000 100,000    
Repairs and upgrading to existing concrete staircase to form back-of-house stair, including balustrades, handrails and finishes (rate per flight); 6 nr @ 拢3,000 18,000    
External walls, windows and doors 1,965,000 143.43 4.98%
Allowance for general repairs and cleaning to brick and stonework facades; 4,500m2 @ 拢150 675,000    
Allowance for replacement of decayed stonework;
1 item @ 拢100,000
100,000    
Allowance for overhauling, easing and adjusting, replacing defective or missing glass and ironmongery and redecorating existing timber sash windows (80% assumed); 250 nr @ 拢4,500 1,125,000    
Allowance for glazed canopy to entrance; 1 item @ 拢50,000 50,000    
Allowance for overhauling, easing and adjusting, replacing defective or missing ironmongery and redecorating existing timber external doors; 3 nr @ 5,000 15,000    
Internal walls and partitions 1,092,000 79.71 2.77%
New blockwork partitions to basement and ground floor areas; 140-200 thick; 2,643m2 @ 拢50 132,150    
Acoustic metal stud partitions to bedroom areas; 4,200m2 @ 拢60 252,000    
Moisture resistant partitions to bathrooms; 2,100m2 @ 拢60 126,000    
Allowance for repairs and alterations to retained lift shafts and interior masonry walls; 1 item @ 拢50,000 50,000    
Full height glazed screens to public areas; 500m @ 拢500 250,000    
Acoustic sliding, folding partitions to function rooms; 1 item @ 拢250,000 250,000    
WC cubicles to public areas; 25 nr @ 拢900 22,500    
WC cubicles to back-of-house areas; 20 nr @ 拢450 9,000    
Internal doors 1,160,000 84.67 2.94%
Hardwood doors and frames to front-of-house areas; vison panels; vision panels, ironmongery; 50 nr @ 拢3,000 150,000    
Hardwood bedroom doors and frames; 100 nr @ 拢2,000 200,000    
Hardwood internal bedroom doors; 43 nr @ 拢1,500 64,500    
En-suite doors, hardwood veneers; 150 nr @ 拢1,500 225,000    
Glazed shower doors; 100 nr @ 拢950 95,000    
Hardwood double doors to bedroom corridors;
70 nr @ 拢3,500
245,000    
Painted or melanine-faced doors and hardwood frames; ironmongery; back-of-house areas; 50 nr @ 拢800 40,000    
Keycard access system to bedroom and selected back of house doors; 563 nr @ 拢250 140,750    
Wall finishes 4,681,000 341.68 11.87%
Skimcoat plaster and paint to bedroom and corridor walls generally; 2,500m2 @ 拢25 62,500    
Guestroom walls; plaster and vinyl wallpaper; 2,500m2 @ 拢75 187,500    
Allowance for panelling to guestroom lobbies; 2,500m2 @ 拢200 500,000    
Plaster and vinyl to guestroom guestroom corridor areas; 4,074m2 @ 拢100 407,400    
Dado rail to bedroom corridors; 1,165m @ 拢50 58,250    
Marble wall tilingto bathrooms; 4,985m2 @ 拢200 997,000    
Panelling to front-of-house walls generally; 9,382m2 @ 拢200 1,876,400    
Allowance for enhanced finishes to public and front-of-house areas; 2,375m2 @ 拢200 475,000    
Plaster and paint to back-of-house and corridor walls generally; 7,000m2 @ 拢10 70,000    
Whiterock cladding to kitchen areas; 400m2 @ 拢65 26,000    
Ceramic tiling to back-of-house toilets and changing areas; 100m2 @ 拢55 5,500    
Sealer to concrete or block walls in plant and workshop areas; 500m @ 拢10 5,000    
Allowance for wall protection rails and guards; 1 item @ 拢10,000 10,000    
Floor finishes 1,447,000 105.62 3.67%
Guestrooms; carpet floor finishes; 1,829m2 @ 拢100 182,900    
Bathrooms; marble tiling; 1,062m2 @ 拢200 212,400    
Allowance for marble surrounds to bedrooms; 1,455m2 @ 拢200 291,000    
Guestroom corridors; carpet floor finishes; 873m2 @ 拢100 87,300    
Lobby and reception; marble flooring; 1,052m2 @ 拢220 231,440    
Hardwood floor to banquet area; 475m2 @ 拢220 104,500    
Carpet to lounge and restaurant areas; 988m2 @ 拢150 148,200    
Other public areas; ceramic/timber/carpet; 918m2 @ 拢100 91,800    
Vinyl flooring and skirtings - back of house; 2,415m2 @ 拢25 60,375    
Allowance for floor sealer to plant and workshop areas; 1,468m2 @ 拢15 22,020    
Matwell to entrance; 1 item @ 拢15,000 15,000    
Ceiling finishes 1,091,000 79.64 2.77%
Guestrooms; plasterboard suspended ceilings; 4,346m2 @ 拢80 347,680    
Guestroom corridors; plasterboard suspended ceilings; 873m2 @ 拢100 87,300    
Lobby and reception ceilings; plasterboard ceiling features; 1,052m2 @ 拢200 210,400    
Other public area ceilings; 2,381m2 @ 拢120 285,720    
Back of house; plasterboard/metal tile suspended ceilings; 2,415m2 @ 拢60 144,900    
Allowance for insulation to plantrooms soffits; 1,468m2 @ 拢10 14,680    
Furniture and fittings 3,259,000 237.88 8.27%
Fitted stone vanity units, mirrors and shower screens to bedrooms; 72 nr @ 拢7,000 504,000    
Fitted stone vanity units, mirrors and shower screens to suites; 28 nr @ 拢25,000 700,000    
Fittings to guestroom corridors; 873m2 @ 拢120 104,760    
Allowance for fitted furniture and fittings to public areas including foyer, restaurant (Loose furniture and bar, lounge, meeting and function rooms fittings to front of house and guestrooms included in FF&E budget); 1 item @ 拢1,200,000 1,200,000    
Allowance for fitted furniture and fittings to back of house areas including stores, changing, pantires etc, (Loose furniture and bar, lounge, meeting and function rooms fittings to front of house and guestrooms included in FF&E budget); 1 item @ 拢750,000 750,000    
Sanitary fittings 821,000 59.93 2.08%
Sanitaryware and fittings to guest bathrooms; 72 nr @ 拢5,500 396,000    
Sanitaryware and fittings to suites; 28 nr @ 拢10,000 280,000    
Sanitaryware and fittings to front of house; 1 item @ 拢85,000 85,000    
Sanitaryware and fittings to back of house; 1 item @ 拢60,000 60,000    
Services equipment 2,500,000 182.48 6.34%
Installation of kitchen and servery equipment including bar and refrigeration fittings, complete;
1 item @ 拢2,500,000
2,500,000    
Disposal installations 431,000 31.46 1.09%
Waste, soil and vent pipework to the hotel generally; 13,700m2 @ 拢30 411,000    
Rainwater installation; 1 item @ 拢20,000 20,000    
Hot and cold water installations 479,500 35.00 1.22%
Cold water storage tank; local electric hot water heaters; hot and cold water insulated copper pipework, valves and accessories to all areas; 13,700m2 @ 拢35 479,500    
Space heating air treatment and ventilation 2,624,500 191.57 6.66%
Air-conditioning to all areas; main plant; ductwork, pipework, insulation, terminal units, grilles and diffusers ; 13,700m2 @ 拢115 1,575,500    
Heated towel rails and electric underfloor heating to bathrooms; 100 nr @ 拢900 90,000    
Extract ventilation to guest rooms; front and
back-of-house areas; main plant; ductwork, pipework, insulation; 13,700m2 @ 拢70
959,000    
Electrical installation 2,450,000 178.83 6.21%
Mains and sub-mains distribution; 13,700m2 @ 拢20 274,000    
Lighting installation to front and back of house; luminaires; emergency lighting; 8,130m2 @ 拢70 569,100    
Small power to front and back of house; 8,130m2 @ 拢22 178,860    
Allowance for additional feature lighting to public areas; 1 item @ 拢250,000 250,000    
Lighting installation to guest rooms and corridors luminaires; emergency lighting; 100 nr @ 拢4,000 400,000    
Small power to guestrooms ; 5,200m2 @ 拢20 104,000    
Fix only allowance for connecting lighting and appliances included in FF&E; 200 nr @ 拢500 100,000    
Electrical supplies to mechanical plant, including guest room ventilation units; 1 item @ 拢40,000 40,000    
Allowance for external building lighting; 1 item @ 拢250,000 250,000    
Standby generator for life safety and essential services; 1 item @ 拢75,000 75,000    
Allowance for earthing and bonding; 13,700m2 @ 拢4 54,800    
Allowance for incoming electrical supply including substation and transformer; 1 item @ 拢150,000 150,000    
Gas installations 25,000 1.82 0.06%
Gas installation; 1 item @ 拢25,000 25,000    
Lift installations 2,725,000 198.91 6.91%
Public lifts; 5 nr @ 拢250,000 1,250,000    
Service/firefighting lift; 9 nr @ 拢125,000 1,125,000    
Dumb waiters; 7 nr @ 拢50,000 350,000    
Protective installations 281,600 20.55 0.72%
Lightning protection; 1 item @ 拢35,000 35,000    
Sprinkler protection to whole hotel; 13,700m2 @ 拢18 246,600    
Communication installations 986,500 72.01 2.50%
Fire alarm and smoke detection system, zoned; 13,700m2 @ 拢12 164,400    
Disabled WC alarm system; 10 nr @ 拢1,500 15,000    
Sound and voice alarm systems; 13,700m @ 拢15 205,500    
Allowance for cable containment; 13,700m2 @ 拢8 109,600    
Telephone and data cabling; 13,700m2 @ 拢9 123,300    
Audio and TV distribution network; 13,700m2 @ 拢12 164,400    
Security, CCTV and access control systems; 13,700m2 @ 拢14 191,800    
Bedroom door access cabling; 100 nr @ 拢125 12,500    
Specialist installations 205,500 15.00 0.52%
黑洞社区 management system and controls; 13,700m2 @ 拢15 205,500    
Builder鈥檚 work in connection 675,000 49.27 1.71%
Forming holes and chases; 1 item @ 拢675,000 675,000    
Main contractor鈥檚 overheads and profit 710,000 51.82 1.80%
Main contractor鈥檚 overheads and profit on services @5%; 1 item @ 拢710,000 710,000    
Preliminaries 6,830,000 498.54 17.32%
Management costs, site establishment and site supervision. Contractor鈥檚 preliminaries, overheads and profit @ 15%; 1 item @ 拢4,890,000 4,890,000    
Testing and commissioning of building services installations; 1 item @ 拢40,000 40,000    
Design reserve at 5%; 1 item @ 拢1,900,000 1,900,000    
Total construction cost      
黑洞社区 only 39,430,100 2,878.11 100%
square metre rate based on GIFA)      
FF&E items 3,416,500 249.38  
Bedroom and front-of-house items; 8,652m2 拢350 3,028,200    
Back-of-house items; 3,883m2 拢100 388,300    
Overall cost including FF&E 42,846,600 3,127.49