New build supermarket with 50,000 ft2 sales area |
Ìý | element cost | cost/m2 gfa £ | % of total cost |
Supermarket fit-out | Ìý | Ìý | Ìý |
Internal partitions & doors | 237,000 | 31.47 | 4.71 |
Internal metal stud partitions, including sundry metalworkÌý2160 m2 @ £55 |
Fire protection / stoppingÌý2160 m2 @ £20 |
Carpentry and joinery including internal doors and frames and trucking doorsÌýItem @ £50,000 |
Security and fire shutters generallyÌýItem @ £25,000 |
Internal finishes | 338,200 | 44.91 | 6.72 |
300 x 300 terrazzo flooring to sales areaÌý5100 m2 @ £35 |
Checkout duct coversÌýItem @ £25,000 |
Allowance for Aluminium access covers and framesÌýItem @ £5,000 |
150 x 150 white wall tiles to bakery, including epoxy groutÌý440 m2 @ £32 |
150 x 150 ceramic floor tiles to bakery, prep areas, serveries and WC's, including epoxy grout, skirtings, angles, etcÌý540 m2 @ £45 |
Vinyl sheet flooring to back-up areas, including skirtings, trims, DPMÌý425 m2 @ £48 |
Allowance for other miscellaneous wall / floor finishesÌýItem @ £25,000 |
Suspended ceilings to domestic areas and customer WC'sÌý465 m2 @ £45 |
Allowance for insitu finishes, including screeding, etcÌýItem @ £25,000 |
Fittings and equipment | 1,309,000 | 173.84 | 26.01 |
Allowance for internal signageÌýItem @ £18,000 |
Allowance for trolley protection railsÌýItem @ £20,000 |
Allowance for ATM / cash officeÌýItem @ £30,000 |
Specialist joinery to create front brand wallÌýItem @ £20,000 |
Shopfitting to PharmacyÌýItem @ £30,000 |
Allowance for gondolas to sales floor generallyÌý4,645 m2 @ £38 |
Servery, plant and equipment to bakeryÌýItem @ £260,000 |
Shopfitting to specialist areas including hot food, deli, meat and fish, salad bar, etcÌýItem @ £130,000 |
Allowance for checkouts (not including service desk and kiosk)Ìý30nr @ £3,000 |
Allowance for miscellaneous shopfitting/specialist items, etcÌýItem @ £150,000 |
Fitting out to customer restaurant (excluding catering equipment)Ìý300 m2 @ £835 |
Fitting out to staff WCsÌýItem @ £16,000 |
Fitting out to staff dining roomÌýItem @ £45,000 |
Allowance for fit-out to staff offices / meeting room / training roomÌýItem @ £15,000 |
Allowance for racking to bulk stock areasÌýItem @ £50,000 |
CompactorÌýItem @ £8,000 |
Water installations | 30,000 | 3.98 | 0.59 |
Allowance for plumbing and water installationÌýItem @ £30,000 |
Services equipment | 734,800 | 97.58 | 14.60 |
Refrigeration distribution installation complete; including pipework and installationÌýItem @ £150,000 |
Refrigeration plant, including packs and condensers (2nr 200kW dual temperature systems)ÌýItem @ £140,000 |
Refrigeration cabinets to shopfloor, including mixture of full height glass door cabinets, opentop cabinets, etcÌý4,645 m2 @ £85 |
Packaged coldstores including controls, etcÌýItem @ £50,000 |
Space heating, air treatment and ventilation | 468,900 | 62.27 | 9.32 |
Ventilation ductwork including insulation, grilles, diffusers, etcÌý7,530 m2 @ £26 |
Air treatment plant, air handling units and central boiler plant supplyingÌý18 m2/s at 30degC 7,530 m2 @ £21 |
Pipework to heating systemÌýItem @ £95,000 |
Allowance for special attenuationÌýItem @ £20,000 |
Electrical installation | 507,500 | 67.40 | 10.08 |
Mains and sub-mainsÌý7,530 m2 @ £11 |
Trays and trunkingÌý7,530 m2 @ £6 |
Small powerÌý7,530 m2 @ £7 |
General lighting to sales floor (800-1,000 lux)Ìý4,645 m2 @ £28 |
Allowance for feature lighting to sales floorÌý4,645 m2 @ £10 |
Back of house lightingÌý2,885 m2 @ £15 |
Power to services installations; containmentÌýItem @ £27,000 |
Allowance for electrical works to specific departments / customer restaurantÌýItem @ £80,000 |
Lift installations | 100,000 | 13.28 | 1.99 |
Allowance for 8 person goods lifts to first floorÌý2nr @ £30,000 |
Scissor lift to service yardÌýItem @ £20,000 |
Dock levellers / sheltersÌý2nr @ £10,000 |
Protective installations | 154,600 | 20.53 | 3.07 |
Allowance for sprinkler installationÌý7,530 m2 @ £20 |
Earthing and bondingÌýItem @ £4,000 |
Communications installation | 154,400 | 20.50 | 3.07 |
Fire alarm installationÌý7,530m2 @ £8 |
Public address systemÌý7,530m2 @ £1 |
Telephone installationÌýItem @ £5,000 |
Structured cablingÌýItem @ £20,000 |
Allowance for CCTV installationÌý19nr @ £1,400 |
Security TaggingÌýItem @ £35,000 |
Special installations | 270,000 | 35.86 | 5.37 |
BMS / controlsÌýItem @ £85,000 |
Allowance for catering equipment to customer restaurant (115 covers)ÌýItem @ £185,000 |
Builder's work | 150,000 | 19.92 | 2.98 |
Allowance for builder's work in connection with services say @ 6%ÌýItem @ £150,000 |
Preliminaries and contingency | 578,000 | 76.76 | 11.49 |
Contractor's site establishment and supervision @ say 6%ÌýItem @ £267,000 |
Contractor's overheads and profit @ say 4%ÌýItem @ £189,000 |
Contingency @ say 2.5%ÌýItem @ £123,000 |
TOTAL CONSTRUCTION COST (Rate based on GIFA of extended store) | 5,032,400 | 668.30 | 100.00 |