A three-house terrace in the east end of London, built entirely from aircrete blocks, is the testing ground for a fast, efficient, hassle-free construction system that could revolutionise housebuilding. Andy Pearson finds out whether it lives up to expectations
A narrow street in one of the less salubrious parts of east London is the unusual setting for a groundbreaking construction project. Squeezed onto a tiny site behind the chip shops and garish fast food outlets that line Bethnal Green Road, housebuilder Laing Partnership is pioneering a construction system. It hopes to build well-insulated dwellings quicker and cheaper, regardless of the weather and without the need for a fully skilled workforce.

Hidden from the road by a shroud of scaffolding, the partially completed terrace of three houses looks much like any other. But step inside and the difference in their construction is immediately apparent 鈥 lightweight concrete blocks and panels have been used everywhere. When they are complete in May, these will be the first houses in the UK to have a structure constructed entirely from aircrete maker H+H Celcon's J盲mer盲 system. The building's walls and foundations are constructed from aircrete blocks, the floors and roof are formed from aircrete planks even the lintels spanning the doors and windows are 鈥 you guessed it 鈥 aircrete.

Aircrete is made of a mixture of materials including ground sand, pulverised fuel ash cement, lime, aluminium powder and water. These are blended together into a mixture that foams, trapping air in the cementitious matrix. This is then cut into sections before it fully hardens, to create solid, light, strong blocks, which, because of their air bubbles, also have good insulating properties. The system is not new; it has been used in Scandinavia for almost 20 years. However, Celcon has adapted the Scandinavian version for the UK market and is about to roll out the complete system in the UK.

Victoria Park Housing Association, the owner of the plot, was looking to trial different construction technologies on this site. The association had originally planned to pioneer an American steel frame system but "negotiations broke down", according to Peter Marten, development director of Laing Partnership, the social housing arm of the Laing Homes Group. "We were keen to find an alternative to timber frame," explains Marten, "because there is still resistance to the use of timber frame by some registered social landlords." Marten says J盲mer盲 offered an alternative form of construction for this diminutive site, and it is expected to cost the same as using traditional brick-and-block masonry.

To measure the success of the system, Laing Partnership is to benchmark the project. The housebuilder has an innovation evaluation group, but for this project they also involved BRE, which is undertaking a government-funded study on sustainability and prefabrication. However, BRE wanted a similar brick-and-block-built terrace for the purposes of comparison. "Laing Partnership doesn't tend to build three-unit schemes," explains Marten. "So we had to identify three similar units on a much larger site in Edmonton to use as a comparator."

Because Laing Partnership was looking to roll out the system on other schemes, it involved Tower Hamlets 黑洞社区 Control and Housing Association Property Mutual 鈥 the building defects insurer for RSLs. "These bodies help give the project independent verification," Marten explains. And the housing association was also able to secure innovation funding from the social housing funder the Housing Corporation.

To eliminate the differences in ground conditions, both projects are being timed from the ground floor upward. Below ground on the J盲mer盲 site, the building's walls are constructed from 350 mm wide, 240 mm deep and 430 mm long blocks. The ground floor panels sit on top of these walls, separated from them by a dampproof course. "Using aircrete for both the ground floor and the foundations means that additional insulation is not needed to comply with the requirements of the new Part L," says Ian Exall, marketing manager at H+H Celcon.

The ground floor is constructed from slabs of reinforced aircrete. These elements are 600 mm wide, 250 mm deep and up to 6 m long, and slot together using a tongue-and-groove system. The planks are craned straight from the delivery truck into position. Once in place, grout binds and seals the panels together. Manufacturing tolerances mean the floor panels are relatively flat. "They do not need a big floor screed, just a thin finishing and levelling screed," Exall explains. In this scheme, the panels used to construct the ground floor were also used for the floor and ceiling of the intermediate floor.

As with the foundations, the external walls are constructed from a single skin of the same 350 mm wide blocks. The blocks are assembled using Celcon's thin-joint mortar system, which uses a 3 mm mortar joint between the blocks rather than the more conventional 10 mm thick trowel-applied mortar. The disadvantage of the system is that there is little scope for correcting inconsistencies. "The key to the wall construction is to ensure the first course of blocks is absolutely level," says Marten. Here, the first course of blocks is bedded on a 10 mm thick layer of mortar.

The wall's single-skin construction means it can be built very quickly. Exall says: "This is down to a combination of not having to construct a cavity and the quick-setting qualities of the thin joint mortar." Originally, the intention was to construct the walls from 300 mm thick blocks, but for the walls to comply with energy regulations their thickness had to be increased to 350 mm, giving the walls a U-value of 0.32 W/m2掳C.

For this project, the reinforced aircrete lintels that span the doors and windows had to be imported from Celcon's Finland plant. The units are fabricated from the same material as the walls, which eliminates the problem of cold bridging. Unfortunately, these elements were not fabricated to the same height as the blocks used to construct the walls, so aircrete packing pieces had to be inserted beneath the lintels. Once Celcon's UK factory starts to produce lintels later this year, such inconsistency will not be a problem.

On site, the houses are almost complete. A crew of bricklayers is adding the final few blocks to the gables, ready the for installation of the aircrete roof panels. Once again, these will be the same as those used to construct the floors. The panels are slotted together lengthways to span between the gables, eliminating the need for a trussed rafter system and allowing an additional room in the roof to be created. Counter battens and tiles will then be added to give the roof a traditional appearance, and an additional 50 mm thick quilt of insulation inserted between the battens will ensure the house is sufficiently insulated to meet the new Part L.

The system has certainly found favour with the team on site. "I work for myself and the rain we've had this week would normally mean that I'd have to stop work," says Rob Peters, contracts manager at Steve Murphy Brickwork. However, the thin joint system means that work can continue whatever the weather. In fact the aircrete system has already proved itself to be faster than the traditional methods used on the comparator project: so much so that the J盲mer盲 team was forced to stop work to allow the Edmonton project to catch up.

Another advantage 鈥 as Peters is quick to point out 鈥 is that, aside from himself, there is only one other skilled bricklayer on the site 鈥 "to ensure the walls are set out correctly". The simplicity of the system means that it is being assembled by an apprentice and a couple of trainees. And because there are no carpenters on site, the same team that built the walls has assembled the floors and roof structure.

The measurement of the comparison between this site and the one in Edmonton, which was started on 14 January, will stop once the finishes have been applied. The smooth wall finish created by the thin joint mortar system means that a thin spray coating of plaster is all it takes to finish the interior. The only preparation needed prior to the application of plaster is to run a rasp over any projecting areas of mortar. Externally, Laing Partnership will be testing a combination of three different finishes: untreated hardwood, the "Corium" brick cladding system, and spray-applied unplasticised render. However, the housebuilder could have chosen any finish for outside of the dwellings, as the single-skin walls already comply with energy regulations.

Laing Partnership is optimistic that the J盲mer盲 scheme will pass the comparison test with flying colours. In fact, the firm is looking to use the system on blocks of flats and apartments. For now, though, the building's new tenants must wait for the builders to finish. And who knows? By then Celcon may even have launched a range of aircrete furniture to fill their aircrete houses.

Cheapness and light: the attractions of a polystyrene prefab house

While Laing Partnerships is using aircrete for the first time, Bellway Homes has just completed its first polystyrene house, writes Thomas Lane. It is a five-bedroom executive-style home that will be marketed alongside its conventional brick-built cousins at Bellway鈥檚 Wynyard Woods development on Teesside. The system is called the external insulation and finishing system and consists of a lightweight steel frame to which polystyrene panels are attached. These are finished with a coating that protects the polystyrene from the weather and impact damage. The system is claimed to have excellent thermal properties, low maintenance requirements and is quick to build. Bill Brown, managing director of drylining and partitioning specialist WA Browne, which holds the UK rights to the system, says the walls have a U-value of 0.2 W/m2掳C. Barry Miller, Bellway Homes鈥 managing director for north-east England, is also enthusiastic as he sees the system as one way of beating the skills shortage. 鈥淭he great thing for us is speed,鈥 he says. 鈥淭o build a 325 m2 house from slab to roof takes five days, rather than the 10 weeks for a conventional home.鈥 With economies of scale, it should also be cheaper to build than a conventional home in the longer term. The 100 mm thick prefabricated panels are simply cut to size using hot wires in WA Browne鈥檚 factory. Architectural features including cornices and window sills are also made from polystyrene and can be incorporated into the panel or glued on afterwards. The panels are shipped to site and bolted to the outside of the 105 mm deep frame over a 15 mm thick fire check exterior grade plasterboard. Internally a 15 mm fire check plasterboard is also used, and the walls and services are run inside the cavity formed by the steel frame. The key to the system is the exterior coating. A specially developed acrylic-based polymer is trowel-applied to the polystyrene. A fibreglass mat is stuck to this, and another coat is applied on top. A finish coat 鈥 which can be any colour 鈥 containing aggregate is then applied. Aggregates of different grades are used, depending on whether a sandstone look or something closer to pebbledash is required. The coating is only 5 mm thick, and is flexible and crack resistant. It acts as a protective shell, having been tested for impact resistance as part of the accreditation process for BBA approval. In the event of damage, localised repairs can be made, although this is a specialised job. Bellway will market the finished house at the same price as the conventionally built homes. Miller says: 鈥淭here is always the possibility buyers will baulk at it. We are selling it at the same price as the other houses to gauge customer reaction.鈥 Bellway will monitor the energy consumption and quality of finish for 12 months after it is finished. Miller is confident the house will stand up to the test well as the system is tried and tested. Developed in Germany after the Second World War as a way to rebuild the country, polystyrene has been used extensively in the USA. Brown built his own house from the material seven years ago and this has proved useful in persuading people that the system is more durable than a giant coffee cup 鈥 one house in Austria is 40 years old. Brown believes skills shortages and the Egan agenda have changed attitudes, and he is now getting enquiries from as far away as Portugal. He believes buyers will warm to the idea of a polystyrene house once they appreciate the benefits of low energy costs and maintenance. For both Brown and Bellway, the bottom line will be the acid test of success.