The parties entered into a JCT With Contractor鈥檚 Design contract for the construction of 114 residential apartments in Manchester. This case concerns the enforcement of an adjudicator鈥檚 decision. During the adjudication, Crosby Homes raised three jurisdictional challenges:
1 There was no jurisdiction under the 鈥渟ide agreements鈥
2 If there was an agreement it was not in writing
3 If there was a written agreement then it was not a construction contract.
Two main issues arose at trial. First, under the main contract, does the adjudicator have jurisdiction in respect of disputes arising 鈥渦nder the contract鈥, or does his jurisdiction extend to disputes 鈥渦nder, out of or in connection with the contract鈥. Second, were the disputes referred to the adjudicator arising 鈥渦nder鈥 and/or 鈥渙ut of or in connection with鈥 the contract?
Reference
The contract had been amended. Article 5 provided that 鈥渋f any dispute or difference arises under this contract鈥 then either party could refer that matter to adjudication in accordance with clause 39A. Amended clause 39A.1 provided that either party may refer any dispute or difference 鈥渁rising under out of or in connection with this contract to adjudication [emphasis added]鈥. The scope of Clause 39A.1 was therefore potentially wider than Article 5.
The defendant argued that Article 5 prevailed but Mr Justice Ramsey held that the contract needed to be read as a whole and that particular emphasis should be given to the bespoke amendments to the standard form that had been agreed between the parties. The adjudicator therefore had jurisdiction to consider disputes arising under, out of or in connection with the main contract.
In October 2004 the parties had reached two agreements. The second October agreement was alleged to have waived liquidated damages and introduced a bonus scheme. Crosby argued that the disputes arose under the alleged side agreement, which was not in writing or was not a construction contract.
The Mr Justice Ramsay considered that the key issue was whether the side agreement was a separate settlement agreement or was a variation to the original contract. He held that unlike Shepherd Construction v Mecright the second October agreement in this case was not a full and final settlement agreement.
The true effect of the side agreement was to introduce a bonus system and relief to liquidated damages, which was a variation to the contract. While the parties, in the side agreement, did not specifically refer to the terms of the contract, it was clear that the effect of the side agreement was to amend provisions of the contract. As the side agreement amended the contract, and the contract contained a wide dispute resolution clause, then an officious bystander would conclude that the dispute resolution procedure under the contract applied to the side agreement. At paragraph 52 he stated:
鈥淚n this case, I consider that the side agreements fell into this category of agreements. It was necessary to have regard to the underlying contract, in particular to see what liquidated damages had been waived. As a result, because, in my judgment, the side agreements were variations to the contract, I consider that the disputes under those side agreements would be properly categorised as disputes under the contract.鈥
He went onto hold that the phrase 鈥渙ut of or in connection with鈥 was wider than 鈥渦nder鈥 the contract, and so even if the side agreements were separate obligations, then they arose out of or in connection with the contract such that the adjudicator had jurisdiction in any event. Brown was therefore entitled to summary judgment.
*Full case details: L Brown & Sons Limited v Crosby Homes (North West) Limited, 5 December 2005, TCC, The Honourable Mr Justice Ramsey, [2005] EWHC 3503
Postscript
This is another decision relating to adjudication. It is interesting for two reasons. First, the dispute resolution clause in the main contract had been amended in order to include disputes arising 鈥渙ut of or in connection with鈥 the contract. The defendants tried to argue that there was a conflict between the narrowly drafted Article 5 and the wider bespoke amendment to the contract. The judge came to the conclusion that there was no conflict between these provisions, and that one simply needed to read the contract as a whole to conclude that the wider interpretation was the correct one.
Second, side agreements can fall into two categories. First, a settlement agreement is an entirely separate contract, albeit that it may settle disputes arising under the main contract. However, the second category of side agreements are ones that merely vary the original contract. A side agreement does not need to specifically refer to the clauses in the main contract. If the side agreement has the effect of varying the terms of the original contract then that is sufficient. A side agreement that simply varied a contract would be caught by the dispute resolution provisions in the original contract. If the side agreement were truly a separate settlement agreement, then an adjudicator may still have jurisdiction if the dispute resolution clause under the main contract was widely drafted. In other words, if the dispute resolution clause covered any disputes arising under or 鈥渙ut of or in connection with鈥 the original contract.