Breakdown of building costs
ºÚ¶´ÉçÇø element Cost (£)
Substructure/foundations 2 308 000
Superstructure/framework 3 520 000
Floors 616 000
Walls 3 192 000
Roofs 1 689 000
ºÚ¶´ÉçÇø finishes 238 000
ºÚ¶´ÉçÇø services 335 000
Total 11 898 000
Costs are outturn costs in November 1998 for buildings only, excluding
process plant and client’s design fees. The buildings have a footprint of
830/m2 and comprise de-watering hall, control room, incinerator hall,
gas clean-up hall, workshop, ash silo enclosure, sub-station, gatehouse.