Elemental cost analysis (final costs)
(gross internal floor area 6452 m2) Total cost (£) Cost per m2 (£) % of total cost
Demolition 13 500 2.09 0.36
Substructure and drainage 1 029 564 159.58 27.78
WC pods 17 380 2.69 0.47
Steelwork 532 930 82.6 14.38
Roof and wall cladding 435 517 67.5 11.75
Curtain walling, windows and doors 172 550 26.74 4.66
Roller and fire shutter doors 84 704 13.13 2.29
Internal blockwork 47 752 7.4 1.29
Fit-out 240 315 37.25 6.48
Signage 4 948 0.77 0.13
M&E installations 644 841 99.95 17.4
Dividing screens 5 542 0.86 0.15
Miscellaneous metalwork 16 797 2.6 0.45
Builders work in connection with services/firestopping 63 648 9.87 1.72
Hard landscaping 100 671 15.6 2.72
Soft landscaping 12 423 1.93 0.34
Preliminaries 283 353 43.92 7.64
Total cost 3 706 435 574.49 100