Cost breakdown |
Ìý | Element cost (£) | Cost /m2 gfa (£) | % of total cost |
Substructure | 312 600 | 84.49 | 8.99 |
Foundations; isolated pad foundations | Ìý | 50 nr @ | £400 |
Ground slab; 150 mm thick reinforced insitu concrete bed, hardcore; damp-proof membrane; below slab drainage; includes thickening to perimeter | Ìý | 2665 m2 @ | £65 |
Extra for forming swimming-pool tank; excavation; retaining walls, ducts, drainage, etc | Ìý | 480 m2 @ | £250 |
Frame | 239 600 | 64.76 | 6.89 |
Structural steel framing; portal frame; windbracing; allowance based on 35 kg/m2 | Ìý | 130 t @ | £1,100 |
Allowance for trimming steelwork to mezzanine and upper floor plant room areas | Ìý | 25 t @ | £1,250 |
Cold-rolled galvanised steel roof purlins; 1.6 m centres; 4.5 kg/m average weight | Ìý | 1900 m @ | £6 |
Cold-rolled galvanised steel sheeting rails; 1.6 m centres; 5 kg/m average weight | Ìý | 650 m @ | £6 |
Intumescent paint finish; one-hour fire resistance; moisture-resistant finish to pool area | Ìý | 2000 m2 @ | £25 |
Upper floors | 54 800 | 14.81 | 1.57 |
Insitu concrete composite floor slabs; power floating | Ìý | 990 m2 @ | £50 |
Extra for 7.5 kN/m2 floor loading to plant room areas | Ìý | 550 m2 @ | £5 |
Facia detail to exposed edge of mezzanine floor slab | Ìý | 50 m2 @ | £50 |
Roof | 221 100 | 59.76 | 6.36 |
Roof cladding; colour-coated galvanised steel sandwich panels; 60 mm thick urethane insulation | Ìý | 2950 m2 @ | £50 |
Extra for 7.5 kN/m2 floor loading to plant room areas | Ìý | 550 m2 @ | £5 |
Facia detail to exposed edge of mezzanine floor slab | Ìý | 50 m @ | £50 |
Stairs | 35 300 | 9.54 | 1.01 |
Steel feature stair and half landing; overall rise 3.50 m; polyester powder-coated mild steel balusters; stainless steel handrails; finishes | Ìý | 1 nr @ | £10 000 |
Insitu concrete stairs and half landing; overall rise 3.50 m; polyester-coated, mild steel handrails; finishes | Ìý | 2 nr @ | £4,500 |
Balustrade and handrail to mezzanine; polyester powder-coate mild steel balusters, stainless steel handrail | Ìý | 18 m @ | £350 |
Allowance for access platforms and stairs to plant rooms | Ìý | Item @ | £10 000 |
External walls | 95 500 | 25.81 | 2.75 |
Wall cladding; colour-coated galvanised steel sandwich panels; 60 mm thick urethane insulation; flashings; accessories | Ìý | 295 m2 @ | £60 |
Cavity wall; fair-faced architectural blockwork; cavity; insulation; 140 mm blockwork inner leaf; windposts etc | Ìý | 740 m2 @ | £85 |
Louvre panels; powder-coated aluminium | Ìý | 30 m2 @ | £250 |
140 mm thick blockwork backing to wall cladding; windposts | Ìý | 295 m2 @ | £25 |
Windows and external doors | 89 700 | 24.24 | 2.58 |
Aluminium-framed; thermally broken windows; sealed double-glazed units with body tinted outer pane; polyester powder coating | Ìý | 235 m2 @ | £300 |
Aluminium-framed shopfront; sealed double-glazed units with body-tinted outer pane; polyester powder coating; 2 nr entrance door sets; ironmongery | Ìý | 20 m2 @ | £600 |
Aluminium double doors and frames; powder-coated; vision panels; ironmongery | Ìý | 6 nr @ | £1,200 |
Internal walls and partitions | 151 100 | 40.84 | 4.35 |
Blockwork partitions; 140 mm average thickness | Ìý | 1500 m2 @ | £22 |
Metal stud partitions; two layers wall board each side; insulation | Ìý | 720 m2 @ | £35 |
Aluminium framed glazed partition; single-glazed units with toughened safety glass; manifestation marking | Ìý | 265 m2 @ | £280 |
Extra for sealed double-glazed units to pool area | Ìý | 165 m2 @ | £50 |
Toilet cubicle partitions | Ìý | 13 nr @ | £650 |
Melamine-faced solid laminate access ducting | Ìý | 20 m @ | £100 |
Internal doors | 71 500 | 19.32 | 2.06 |
Flush doors; fire-rated; solid core laminate/veneer-faced; hardwood frames; decorations; ironmongery; complete | Ìý | 60 nr @ | £750 |
Flush doors; non-fire-rated; solid-core laminate/veneer-faced; hardwood frames; decorations; irnomongery; complete | Ìý | 30 nr @ | £650 |
Extra over aluminium-framed glazed partitions for doors and frames; ironmongery; complete | Ìý | 7 nr @ | £1,000 |
Wall finishes | 68 300 | 18.46 | 1.96 |
Ceramic tiles; to blockwork or plasterboard | Ìý | 700 m2 @ | £45 |
Extra for sand cement backing to ceramic tiles; to blockwork | Ìý | 535 m2 @ | £8 |
13 mm two-coat lightweight plaster; two coats emulsion paint; to blockwork | Ìý | 1960 m2 @ | £10 |
Two coats emulsion paint; to blockwork | Ìý | 1130 m2 @ | £3 |
Extra for water resistant paint finish to pool hall | Ìý | 250 m2 @ | £2 |
Skim coat and two coats emulsion paint to plasterboard | Ìý | 410 m2 @ | £5 |
Waterproof render and mosaic tiles to pool tank sides | Ìý | 100 m2 @ | £70 |
Floor finishes | 190 300 | 51.43 | 5.47 |
Sand cement screed; average 50 mm thick | Ìý | 2700 m2 @ | £8 |
Heavy-duty carpet tiles | Ìý | 1900 m2 @ | £35 |
Painted hardwood skirting | Ìý | 700 m @ | £10 |
Timber strip flooring; to reception and bar etc; including skirtings | Ìý | 190 m2 @ | £55 |
Semi-sprung beech strip flooring to aerobics room; including skirtings | Ìý | 100 m2 @ | £65 |
Ceramic tiles to dry changing areas; including ceramic coved skirting | Ìý | 150 m2 @ | £50 |
Non-slip ceramic tiles to wet changing areas and pool surround; including ceramic coved skirting | Ìý | 320 m2 @ | £65 |
Extra for edge tile and grating to pool perimeter | Ìý | 75 m @ | £110 |
Allowance for drainage gullies and gratings to wet change areas | Ìý | Item @ | £2,000 |
Waterproof render and mosaic tiles to pool tank base; including lane markings etc | Ìý | 310 m2 @ | £75 |
Granolithic to plant rooms; skirting | Ìý | 510 m2 @ | £25 |
Mats and matwells | Ìý | Item @ | £5,000 |
Ceiling finishes | 69 500 | 18.78 | 2 |
Acoustic sof lining to pool and gym | Ìý | 1750 m2 @ | £20 |
Suspended ceilings; mineral-fibre tiles; lay in grid; generally | Ìý | 1270 m2 @ | £25 |
Extra over suspended ceilings for moisture-resistant tiles to changing areas | Ìý | 440 m2 @ | £5 |
Extra over suspended ceilings for acoustic tiles to aerobic room | Ìý | 100 m2 @ | £5 |
Furniture and fittings | 289 600 | 78.27 | 8.33 |
(Excluding allowances for gymnasium equipment, loose furniture, catering equipment, loose office furniture, fittings and equipment, music and TV installations) | Ìý | Ìý | Ìý |
Reception desk; turnstile entry control | Ìý | Item @ | £18 000 |
Bar counter and back bar units; roller grilles | Ìý | Item @ | £25 000 |
Vanitory units; mirrors; fittings etc to changing areas | Ìý | Item @ | £20 000 |
Benches to changing areas | Ìý | Item @ | £5,000 |
Lockers | Ìý | 400 nr @ | £200 |
Composite safety mirrors to exercise areas | Ìý | 150 m2 @ | £220 |
Ballet barre; to aerobics studio | Ìý | 12 m @ | £300 |
Allowance for signage, banners, graphics etc to exercise, pool and circulation areas | Ìý | Item @ | £50 000 |
Allowance for supervisor's workstations; noticboards etc, to exercise areas | Ìý | Item @ | £10 000 |
Allowance for fittings to creche | Ìý | Item @ | £10 000 |
Allowance for fixed furniture, noticeboards etc to office areas | Ìý | Item @ | £10 000 |
Allowance for fittings to pool; steps; pool cover; skimmers; pacer clocks etc | Ìý | Item @ | £20 000 |
Allowance for internal planting | Ìý | Item @ | £5,000 |
Sanitary fittings | 36 400 | 9.84 | 1.05 |
WCs, urinals, washhand basins; generally | Ìý | 32 nr @ | £300 |
Extra for fittings for disabled WCs | Ìý | 2 nr @ | £100 |
Showers; cabinets, trays, fittings | Ìý | 24 nr @ | £1,000 |
Cleaners sinks | Ìý | 3 nr @ | £350 |
Drinking water fountain | Ìý | 6 nr @ | £250 |
Disposal installations | 22 000 | 5.95 | 0.63 |
Rainwater disposal; cast iron downpipes and fittings | Ìý | 3700 m2 @ | £2.50 |
Waste, soil and vent installation; uPVC pipework and fittings | Ìý | 73 nr @ | £175 |
Water installations | 34 800 | 9.41 | 1 |
Hot and cold water service; calorifiers; hot and cold water storage; distribution to WCs, changing areas, water fountains etc | Ìý | 116 nr @ | £300 |
Space heating and air treatment | 435 200 | 117.62 | 12.52 |
Gas installation | Ìý | Item @ | £10 000 |
Low-temperature hot-water heating; boiler plant serving swimming pool and space heating; flues; pumps and valves; distribution within plant rooms; insulation | Ìý | 3700 m2 @ | £20 |
Chilled water installation; chiller; pressurisation unit; pumps and valves; distribution within plant rooms; insulation and trace heating | Ìý | 3700 m2 @ | £10 |
Supply and extract ventilation to gym; air-handling unit with heating and cooling batteries; high-level, low-velocity ductwork; diffusers | Ìý | 1250 m2 @ | £65 |
Supply and extract ventilation to pool; air-handling unit with heating battery and heat recovery; high-level, low-velocity ductwork; diffusers | Ìý | 480 m2 @ | £90 |
Supply and extract ventilation; heating and comfort cooling to cellular spaces; air-handling units with heating and cooling batteries; ductwork; insulation; grilles and diffusers | Ìý | 1270 m2 @ | £110 |
Extra for changing room and toilet extract installation; allowance for steam room extract | Ìý | Item @ | £25 000 |
Allowance for kitchen extract installation | Ìý | Item @ | £15 000 |
Plant room ventilation; allowance for chemical extract | Ìý | Item @ | £10 000 |
Electrical installations | 245 800 | 66.43 | 7.07 |
Mains and sub-mains installation | Ìý | Item @ | £50 000 |
Small power distribution | Ìý | 3700 m2 @ | £15 |
Lighting and luminaires to fitness area | Ìý | 1250 m2 @ | £30 |
Lighting and moisture resistant luminaires to pool hall | Ìý | 480 m2 @ | £25 |
Lighting and luminaires to aerobics and ancillary spaces | Ìý | 1780 m2 @ | £35 |
Emergency lighting installation | Ìý | 3700 m2 @ | £5 |
Power to mechanical services | Ìý | Item @ | £10 000 |
Lift installations | 18 000 | 4.86 | 0.52 |
Five-person, 430 kg hydraulic lift serving 2 nr floors; 0.3 m/s | Ìý | Item @ | £18 000 |
Protective installations | 9 300 | 2.51 | 0.27 |
Lightning protection | Ìý | 3700 m2 @ | £1.50 |
Earthing and bonding | Ìý | 3700 m2 @ | £1 |
Communications installations | 127 000 | 34.32 | 3.65 |
Fire and smoke detection and alarm system | Ìý | 3700 m2 @ | £15 |
Public address system | Ìý | 3700 m2 @ | £5 |
TV installation; central aerial, wireways, points and wall mounting brackets (monitors excluded) | Ìý | Item @ | £10 000 |
Intruder detection | Ìý | 3700 m2 @ | £1.50 |
Access control | Ìý | Item @ | £5,000 |
CCTV system; 10 nr cameras | Ìý | Item @ | £25 000 |
Wireways for telephones and data | Ìý | 3700 m2 @ | £2 |
Special installations | 152 500 | 41.22 | 4.39 |
ºÚ¶´ÉçÇø management system | Ìý | 3700 m2 @ | £15 |
Pool filtration system; chlorine based | Ìý | Item @ | £55 000 |
Steam rooms (2 nr) | Ìý | Item @ | £30 000 |
Saunas (2 nr) | Ìý | Item @ | £12 000 |
Builder's work in connection | 54 000 | 14.59 | 1.55 |
Forming holes, chases etc: allow 5% | Ìý | Item @ | £54 000 |
Preliminaries and contingencies | 453 000 | 122.43 | 13.03 |
Contractor's overheads, site establishment and site supervision, excluding design fees; allow 10% | Ìý | Item @ | £302 000 |
Contingency sum: allow 5% | Ìý | Item @ | £151 000 |
Total construction cost - building only | 3 476 900 | 939.69 | 100 |