Keep up to dateElemental cost breakdown, Scottish Gas HQ | ||||
Office building, including fit-out, of 10,568 m2 gross internal floor area, comprising four storeys and basement | ||||
ELEMENT | Total cost £ | Cost £/m2 gifa | % split | Ìý |
SUBSTRUCTURE | 489,000 | 46.03 | 2.39 | rotary and continuous flight auger piles; ground beams; retaining wall; reinforced concrete basement slab |
SUPERSTRUCTURE | Ìý | Ìý | Ìý | Ìý |
Frame and upper floors | 2,598,000 | 244.54 | 12.67 | fully exposed insitu reinforced concrete frame; enhanced finish; coffered floor slabs |
Roof | 376,500 | 35.44 | 1.84 | insitu reinforced concrete slab; Sarnafil roof covering; soffit to external |
Stairs | 341,700 | 32.16 | 1.67 | precast concrete stair cores; feature atrium staircase |
External walls | 2,089,900 | 196.71 | 10.19 | aluminium curtain walling; horizontal sun-screens |
Windows and external doors | 73,600 | 6.93 | 0.36 | revolving main entrance door; pass doors; emergency exit doors |
Internal walls and partitions | 971,700 | 91.46 | 4.74 | core fit-out including cubicles; tenant system partitions; smoke curtains |
Internal doors | 291,900 | 27.48 | 1.42 | timber laminate doors to cores; steel doors to plant areas |
FINISHES | Ìý | Ìý | Ìý | Ìý |
Wall finishes | 89,400 | 8.41 | 0.44 | emulsion paint; tiled splashbacks |
Floor finishes | 727,500 | 68.48 | 3.55 | raised access floors; fixing of diffusers, carpet tiles; granite to reception |
Ceiling finishes | 77,400 | 7.29 | 0.38 | ceiling finishes to the core areas |
Fittings and furnishings | 367,200 | 34.56 | 1.79 | blinds; signage; integrated furniture; mobile racking; kiosk |
SERVICES | Ìý | Ìý | Ìý | Ìý |
Sanitary appliances | 144,400 | 13.59 | 0.70 | Ìý |
Special equipment | 454,000 | 42.73 | 2.21 | kitchen equipment |
Disposal installations | 94,500 | 8.89 | 0.46 | syphonic drainage and waste services |
Water installations | 108,100 | 10.18 | 0.53 | for toilet cores, vending, shower facilities and kitchen areas |
Heat source | – | 0.00 | 0.00 | bought as part of package plant room |
Space heating and ventilation systems | 2,131,000 | 200.58 | 10.40 | displacement ventilation through plenum floor; electric trench heating to glazed areas; ventilating systems passive chilled beams; fan coil units to restaurant areas; stand-alone cooling to communications rooms |
Electrical installations | 2,168,000 | 204.07 | 10.58 | HV/LV substation; landlord’s and small power to desks; lighting; emergency lighting; generator back-up; uninterrupted power supply; sound insulation to generator room |
Gas installations | 14,800 | 1.39 | 0.07 | Ìý |
Lift and conveyor installations | 340,800 | 32.08 | 1.66 | three passenger lifts; one goods lift |
Protective installations | 72,900 | 6.86 | 0.36 | lightning protection; earthing |
Communications installations | 788,300 | 74.20 | 3.85 | fire alarm and voice evacuation; structured cabling; security; data cabling to desks |
Special installations | 461,800 | 43.47 | 2.25 | building management system |
EXTERNAL WORKS | Ìý | Ìý | Ìý | Ìý |
Site works | 587,000 | 55.25 | 2.86 | external car park; extensive soft landscaping; granite plaza area; benches |
Drainage | 150,600 | 14.18 | 0.73 | below ground floor slab and site area |
External services | 131,300 | 12.36 | 0.64 | Ìý |
Minor building works | 3,800 | 0.36 | 0.02 | Ìý |
Trade contractor preliminaries | 1,930,900 | 181.75 | 9.42 | allowances extracted from trade contractor packages |
CM staff, organisation and fees | 2,423,300 | 228.10 | 11.82 | Ìý |
TOTAL | 20,499,300 | 1929.53 | 100.00 | Ìý |
NotesÌýFigures shown cover whole project costs including shell-and-core works, landlord’s category A fit-out, tenant’s category A enhancements and tenant’s category B fit-out and external works. Cost breakdown calculated by converting final accounts, or anticipated final accounts, of trade packages into elemental form. | ||||
Trade packages were tendered between February 2002 and March 2003 |