Balancing act: Breakdwon of costs
ÌýGIA Cost Total Cost
Ìým2 m2 (£) %
Demolition & alterations 3,155 35.82 113,010 1.5
Substructure 3,155 134.92 425,660 5.6
Frame & upper floors 3,155 189.71 598,550 7.8
Roof 3,155 91.01 287,150 3.7
Stairs 3,155 106.56 336,210 4.4
External walls, windows & doors 3,155 219.34 692,010 9.0
Internal walls & partitions 3,155 43.85 138,350 1.8
Internal doors 3,155 82.19 259,320 3.4
Wall finishes 3,155 43.08 135,920 1.8
Floor finishes 3,155 52.87 166,790 2.2
Ceiling finishes 3,155 30.52 96,300 1.3
Fixtures & fittings 3,155 100.00 315,500 4.1
Mechanical & electrical installations 3,155 597.94 1,886,490 24.6
Theatre equipment 3,155 285.22 899,880 11.7
Lift installation 3,155 20.54 64,800 0.8
External works 3,155 43.95 138,670 1.8
External services 3,156 42.14 133,000 1.7
Preliminaries, overhead and profit 3,155 310.11 978,390 12.8
Total construction cost Ìý2,430 7,666,000 100.0
* includes builders work