- Contractor complains of lack of early involvement,
- 鈥楩urther tweaks鈥 due in early 2007,
- Shiplee invites industry feedback
Further changes are expected to hit the budget for the London Olympics after the government confirmed a hike in costs last week.
QS News understands that a review of the cost plan for the scheme, undertaken by delivery partner CLM, will not be completed until early next year.
A source close to the consortium, which includes Mace and Laing O鈥橰ourke, said: 鈥淭he cost plan is still under review. There are bound to be further tweaks.鈥
It is also understood that Davis Langdon, which was part of the winning CLM consortium, has yet to be officially confirmed as the cost manager for the delivery partner. A source close to CLM said that the firm had to re-apply for the position as it was a second-tier role, but an agreement for the firm to join was 鈥渋mminent鈥.
Culture secretary Tessa Jowell confirmed last week a 拢900m increase in the budget for the Olympic park,
due to an increase in steel costs and a 拢400m payment to CLM to ensure the construction programme goes smoothly. This led to criticism that cost control was non-existent on the scheme even before work had begun. Meanwhile, this week the Olympic Delivery Authority (ODA) revealed it has scaled down the Aquatics Centre, designed by architect Zaha Hadid (below right).
Asking anyone what the budget will be is like asking me who will win the 2.30 at Haydock
Michael Byng, RICS
Experts, however, have played down the chaotic picture. One source claimed the team had been hampered by poor communication.
RICS QS faculty chairman Michael Byng said discussion of the budget had been one-sided. Byng said: 鈥淵ou need to look at the receipts coming in from the project, such as with land sales, as well as the expenditure. Right now all we are getting is the expenditure, but this seems like a dynamic business case.
It is inevitable that costs are going to vary because of this. However, asking anyone what the budget will be is like asking me who will win the 2.30 at Haydock on Saturday.鈥
Criticism of the client, the ODA, was voiced last week by the industry. One major contractor claimed the apparent spiralling of costs was due to the lack of early contractor involvement. At the Thames Gateway Forum on 23 November Nick Balmer, business development manager at Edmund Nuttall, said: 鈥淓arly contractor involvement shows whether you are getting value for money even before you set the budget鈥.
Balmer said that clients 鈥渟hould come to us and [say] 鈥榯his what we want to build, how do we go about it?鈥欌
He commented that while recent improvements in procurement were commendable, they had not gone far enough. 鈥淲e have a huge amount of skilled people who are diverted, sometimes for years, by procurement.
It isn鈥檛 right that these talented and creative people are spending all their time filling forms
Nick Balmer, Edmund Nuttall
It isn鈥檛 right that these talented and creative people are spending all their time filling out forms.鈥 Balmer said the Highways Agency鈥檚 move to early contractor involvement was 鈥渆xcellent鈥.
Howard Shiplee, director of construction for the ODA, said in the same conference session that he welcomed a debate about procurement. 鈥淭he comments about procurement are good... We want to know what the industry thinks.鈥
He said the ODA was talking to Team McAlpine, the consortium chosen to design and build the Olympic stadium, in order to establish a collaborative approach based on 鈥渙ne project focus鈥.
He said: 鈥淭here is a lot of debate about design at the moment but a lot of what we are doing is temporary, so we are not going to leave white elephants.鈥
Shiplee added that it was down to the client to 鈥渟et the conditions for the success of a project鈥. He refused to be drawn into questions about the costs of the Olympic project: 鈥淚 am not going to talk about money. It鈥檚 being debated in government.鈥
Source
QS News
No comments yet