Contractor sees off three big name rivals to take 拢600m job to redevelop the Battersea Power Station

battersea power station - phase 2

Skanska has been confirmed as contractor for the prestigious 拢600m job to redevelop the Battersea Power Station.

Skanska had won the race, beating competitors Balfour Beatty, Lend Lease and Mace for the contract to redevelop the iconic grade II* listed power station into a major mixed-use scheme.

In August all four bidders , home of the Malaysian consortium of owners behind the Battersea scheme.

Philip Gullett, chief operating officer at BPSDC, said: 鈥淪kanska鈥檚 appointment to restore and refurbish the Power Station is further demonstration of our shareholders鈥 commitment to the development and a major step towards opening up the Battersea Power Station to the public.

鈥淪kanska is a leading contractor, with the experience and expertise to undertake the work required on this Grade II* listed iconic building.鈥

The 拢600m redevelopment of the power station building, which constitutes the main element of the second phase, will feature retail and events space on the lower floors, 58,000m2 of offices above and 248 flats crowning the building.

The scheme, designed by Wilkinson Eyre, also incorporates a circular glass lift that will emerge out of the top of one of the building鈥檚 rebuilt chimneys, giving visitors views across London.

Mace is acting as construction manager on the 拢100m first element of the second phase, which involves the repair and restoration of the historic structure itself, including the iconic chimneys.

The site handover from Mace to Skanska will complete by the end of November, Battersea Power Station Development Company (BPSDC) said.

Work has already begun on dismantling the first of the 100m-tall chimneys, which together with the other three will be rebuilt using the same concrete and reinforced steel materials but to modern specifications by 2016.

Skanska is already working on phase one of the project, after the firm was awarded a 拢90m contract to fit out 866 homes on the 拢400m first phase, which is being built by Carillion.

Battersea Power Station chimneys

Battersea Power Station chimneys