Legal battle over stadium continues as engineer calls contractor's £253m case 'embarrassing'
Mott MacDonald has labelled Multiplex's £253m claims against it over delays to Wembley stadium, 'embarrassing'.
In the latest twist in the Wembley saga, the engineer filed its defence at the High Court this week, setting out objections to the claims by Multiplex  since bought by contractor Brookfield  over alleged design failings on the much-delayed stadium.
Brookfield filed a writ last December claiming £253m in damages from Mott for failing to warn it of design changes and providing 'late and inadequate' information. Wembley was completed two years late and up to £300m over budget.
But Mott MacDonald claims Brookfield was responsible for the delays and problems. Multiplex has already fought legal battles with subcontractors CBUK and PC Harrington.
Mott claimed Multiplex's case was 'embarrassing and lacking in any proper particulars'. It said a timeline of works was 'irregular', and contained 'logic errors' Â for example, that Multiplex, CBUK and PC Harrington said the rotation of the arch had happened on different dates.
Mott called for further detail and proof that losses were caused by its negligence. It also launched a counterclaim for £230k, mostly in unpaid fees for variations.
A senior construction lawyer said: "The word 'embarrassing' is meant to emphasise that there is a lack of detail in the particulars of the case."
Given the high degree of this in the CBUK case, it's no surprise they've brought it up. He added that Mott MacDonald would now be hoping that the judge would either demand more information from Multiplex's legal team or throw the case out.
1 Readers' comment