Elemental cost analysis
Total cost (£) Cost per unit (£) % of total cost
Site clearance and demolition 34 396 2 150 4.32
Substructure 45 872 2 867 5.76
Superstructure      
Frame 164 914 10 307 20.72
Upper floors 4 944 309 0.62
Roof 46 672 2 917 5.87
Stairs 22 889 1 431 2.88
External walls 44 222 2 764 5.56
Windows and external doors 60 163 3 760 7.56
Internal walls and partitions 24 918 1 557 3.13
Internal doors 31 553 1 972 3.97
Internal finishes      
Wall finishes 16 270 1 017 2.04
Floor finishes 16 872 1 055 2.12
Ceiling finishes 8 771 548 1.10
Decoration 6 835 427 0.86
Fittings, fixtures and furnishings 6 080 380 0.76
M&E installation      
Sanitary appliances 6 835 427 0.86
Water installations 37 086 2 318 4.66
Space heating and air treatment 54 167 3 385 6.81
Ventilating systems 18 891 1 181 2.37
Electrical installations 18 822 1 176 2.37
Communication installations 8 559 535 1.08
Builder’s work in connection with services 175 11 0.02
Total building 679 906 42 494 85.44
Site works 37 273 2 330 4.68
Drainage 9 697 606 1.22
External services 19 394 1 212 2.44
Total construction 746 270 46 642 93.78
Preliminaries 49 460 3 091 6.22
Total cost 795 730 49 733 100